Roads and Footpath Works
Road works are coordinated so as to minimise disruptions to residents, motorists and pedestrians. For example, road works located near residential areas are carried out mostly in the day, and road works near schools and busy roads are scheduled for non-peak hours.
Work on the City’s roads, footpaths and verges can be carried out by a number of different service providers. In general, the City manages the local roads within the local government area and the main, State controlled roads are managed by Main Roads WA.
Roads are condition-rated against a range of criteria to determine the need for, and timing of, preventative or remedial action to prevent loss of service. The ratings address factors such as structure, surface cracking, ride-ability, age and predicted increases in traffic volumes and vehicle classifications.
Current road and footpath news
News Listings
Road Rehabilitation Works - Mill Point Rd, South Perth
The City will be undertaking road rehabilitation works at Mill Point Road, between Coode Street and Douglas Avenue, South Perth. Works will commence on 28 April 2022 and will take approximately 4-5 weeks to complete.
Road Rehabilitation Works - Hobbs Ave, Como
The City will be undertaking road rehabilitation works at Hobbs Avenue, between Murray St and Throssell St, Como. Construction works are scheduled to commence on 4 April 2022 and take approximately 5-6 weeks to complete.
Traffic Warden Controlled Children’s Crossing - Abjornson St and Gillon St, Manning
The City will be installing a new Traffic Warden Controlled Children’s Crossing at the corner of Abjornson Street and Gillon Street, Manning. Scheduled to commence on 5 April 2022 the works will take approximately 3-4 weeks to complete.
Redmond Stairs update
The upgrade to the stairs at Redmond Reserve in Salter Point has encountered some delays. We are anticipating works will be complete by the end of May 2022.
Weekly approved works 21-28 March 2022