South Perth Station Precinct works update: week commencing 6 August
Approved works within the South Perth Station Precinct for the week commencing 6 August 2018:
LOCATION | DETAILS OF WORKS | WHO | DATE | TIME |
Construction site - abnormal works* | ||||
5 Harper Terrace (Reva) |
Harper Terrace half road closure with reversible flow managed by traffic control for internal concrete pour. |
Hanssen | 6 August |
7am-12pm |
Construction site - general approvals** | ||||
39 Mends Street (Echelon) |
Dewatering, shotcreting piled walls, excavation, formwork and concrete pours. Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours. |
Giorgi |
6-11 August |
7am-5pm |
21 Mends Street (Harper Terrace) |
Concrete pouring to slabs/walls, including concrete trucks entering / exiting the site, |
Quest Apartments/Pindan |
6-11 August |
7am-5pm |
1 Stone Street |
Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street. |
Danmar Developments |
6-17 August |
7am-5pm |
5 Harper Terrace (Reva) |
General truck movements on Harper Terrace, remedial work on sinkhole, road and diaphragm wall, minor concrete pours. |
Hanssen |
6-11 August |
7am-5pm |
26 Charles Street |
Bulk earthworks and reduced levels. Some head works for contiguous piles. Preparation for some concrete formwork and reinforcement. |
Pindan |
6-17August |
7am-5pm |
Other works |
||||
South Perth Esplanade |
Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road. |
RAC |
7-12 August |
9am-5pm |
Upcoming works |
||||
21 Mends Street (Harper Terrace) |
Subject to approvals. Tower crane demobilisation with road closure of Harper Terrace. |
Quest Apartments/Pindan |
18 August |
7am-5pm |
South Perth Esplanade |
Subject to approvals. Testing of Autonomous bus on South Perth Esplanade, Mill Point Close and Mill Point Road |
RAC |
13 August |
8.30am-4.30pm |
South Perth Esplanade |
Subject to approvals. Operation of Autonomous bus on South Perth Esplanade, Mill Point Close and Mill Point Road. |
RAC |
31 August |
8.30am-3.30pm |
Mill Point Road (Harper Terrace) |
Subject to approvals. Signage installation on Southbank Building using lane closure on Mill Point Road. |
Design Collision |
1 September |
7am-12pm |
Mends Street (MPR – SPE) |
Subject to approvals. Closure of Mends Street (Mill Point Road – South Perth Esplanade) to facilitate crane operations. |
General / Workforce Road Services |
TBC |
TBC |
39 Mends Street |
Subject to approvals. Footpath closure, pedestrian detour and traffic management on Mends Street to facilitate Western Power connection works for 39 Mends Street. |
Cabling WA |
Late August |
TBC |
To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.
Details of other road works in the City can be found on the construction and maintenance work page of the website.
*Abnormal works
Abnormal works are one off activities that require significant truck movements, obstructions to movement such as road closures and detours or works outside of the normal working hours. These works are subject to a separate approval process and are considered on an individual basis. Approvals may include the need to notify residents of the temporary change and in the case of works outside of normal working hours require subsequent approvals from the City’s Environmental Health Team and CEO.
**General Approvals
General approvals are granted to construction sites and long-term activities in the Station Precinct for daily activities such as general truck movements for deliveries and minor concrete pours. These works are only to be undertaken during normal working hours (7am – 7pm Monday -Saturday) and do not include works that will have a significant impact on access through/past the site area. General works are subject to a monthly approval process.