South Perth Station Precinct works update: week commencing 6 August

Public Notice 3 August 2018
Maintenance Works Road Works SPSP Traffic

Approved works within the South Perth Station Precinct for the week commencing 6 August 2018:

LOCATION DETAILS OF WORKS WHO DATE TIME
Construction site - abnormal works*
5 Harper Terrace (Reva)
Harper Terrace half road closure with reversible flow managed by traffic control for internal concrete pour.
Hanssen 6 August
7am-12pm
Construction site - general approvals**

39 Mends Street (Echelon)

Dewatering, shotcreting piled walls, excavation, formwork and concrete pours. Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours.

Giorgi

6-11 August

7am-5pm

21 Mends Street (Harper Terrace)

Concrete pouring to slabs/walls, including concrete trucks entering / exiting the site,
Mobilisation of minor materials and equipment to site for Plumbing, Electrical & Mechanical Works,
Delivery and Installation of Formwork and Scaffold to Site, including delivery trucks entering / exiting the site.

Delivery and Installation Structural Steel and Roof Sheeting,

Quest Apartments/Pindan

6-11  August

7am-5pm

1 Stone Street

Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street.

Danmar Developments

6-17 August

7am-5pm

5 Harper Terrace (Reva)

General truck movements on Harper Terrace, remedial work on sinkhole, road and diaphragm wall, minor concrete pours.

Hanssen

6-11 August

7am-5pm

26 Charles Street

Bulk earthworks and reduced levels. Some head works for contiguous piles. Preparation for some concrete formwork and reinforcement.

Pindan

6-17August

7am-5pm

Other works

South Perth Esplanade

Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road.

RAC

7-12 August

9am-5pm

Upcoming works

21 Mends Street (Harper Terrace)

Subject to approvals. Tower crane demobilisation with road closure of Harper Terrace.

Quest Apartments/Pindan

18 August

7am-5pm

South Perth Esplanade

Subject to approvals. Testing of Autonomous bus on South Perth Esplanade, Mill Point Close and Mill Point Road 

RAC 

13 August

8.30am-4.30pm

South Perth Esplanade

Subject to approvals. Operation of Autonomous bus on South Perth Esplanade, Mill Point Close and Mill Point Road.

RAC

31 August

8.30am-3.30pm

Mill Point Road (Harper Terrace)

Subject to approvals. Signage installation on Southbank Building using lane closure on Mill Point Road.

Design Collision

1 September

7am-12pm 

Mends Street (MPR – SPE)

Subject to approvals. Closure of Mends Street (Mill Point Road – South Perth Esplanade) to facilitate crane operations.

General / Workforce Road Services

TBC

TBC 

39 Mends Street

Subject to approvals. Footpath closure, pedestrian detour and traffic management on Mends Street to facilitate Western Power connection works for 39 Mends Street.

Cabling WA

Late August

TBC

To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.

Details of other road works in the City can be found on the construction and maintenance work page of the website.

*Abnormal works
Abnormal works are one off activities that require significant truck movements, obstructions to movement such as road closures and detours or works outside of the normal working hours. These works are subject to a separate approval process and are considered on an individual basis. Approvals may include the need to notify residents of the temporary change and in the case of works outside of normal working hours require subsequent approvals from the City’s Environmental Health Team and CEO.
 
**General Approvals
General approvals are granted to construction sites and long-term activities in the Station Precinct for daily activities such as general truck movements for deliveries and minor concrete pours. These works are only to be undertaken during normal working hours (7am – 7pm Monday -Saturday) and do not include works that will have a significant impact on access through/past the site area. General works are subject to a monthly approval process. 

Contact us

For more information, please contact the City or Make a Request online.
  • Phone 9474 0777