South Perth Station Precinct works update: week commencing 30 July

Public Notice 31 July 2018
Maintenance Works Road Works SPSP Traffic

Approved works within the South Perth Station Precinct for the week commencing 30 July 2018:

LOCATION DETAILS OF WORKS WHO DATE TIME
Construction site - abnormal works*
5 Harper Terrace (Reva)
Harper Terrace half road closure with reversible flow managed by traffic control for internal concrete pour.
Hanssen 3 August
7am-12pm
Construction site - general approvals**
39 Mends Street (Echelon) Dewatering, shotcreting piled walls, excavation, formwork and concrete pours. Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours. Giorgi 30 July-4 August 7am-5pm
21 Mends Street (Harper Terrace) Reinforcement steel deliveries and steel fixing, including delivery truck entering/exiting the site, concrete pouring to slabs/columns/walls, including concrete trucks entering/ exiting the site. Mobilisation of minor materials and equipment to site for plumbing, electrical and mechanical works. Delivery and installation of formwork and scaffold to site, including delivery trucks entering/exiting the site. Delivery and installation of precast concrete walls. Delivery and installation of AFS, structural steel and roof sheeting, demolition/cutting of the precast panel, demobilise of Static concrete pump.
Quest Apartments/Pindan 30 July-4 August 7am-5pm
35 Mends Street Painting and Line Marking to Ramp, delivery and installation of formwork to site, including delivery trucks entering/exiting the site delivery. Delivery and installation of roof sheeting, Pindan 30 July-4 August 7am-5pm
1 Stone Street Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street.
Danmar Developments

30 July-4 August

7am-5pm
5 Harper Terrace (Reva) General truck movements on Harper Terrace, remedial work on sinkhole, road and diaphragm wall, minor concrete pours. Hanssen 30 July-4 August 7am-5pm
26 Charles Street Bulk earthworks and reduced levels. Some head works for contiguous piles. Preparation for some concrete formwork and reinforcement.
Pindan 30 July-4 August 7am-5pm
Other works
South Perth Esplanade Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road. RAC 31 July-5 August 9am-5pm
Upcoming works
21 Mends Street (Harper Terrace) Subject to approvals. Tower crane demobilisation with road closure of Harper Terrace. Quest Apartments/Pindan 18 August 7am-5pm
South Perth Esplanade Subject to approvals. Operation of Autonomous bus on South Perth Esplanade, Mill Point Close and Mill Point Road. RAC 31 August 9am-1pm

To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.

Details of other road works in the City can be found on the construction and maintenance work page of the website.

*Abnormal works
Abnormal works are one off activities that require significant truck movements, obstructions to movement such as road closures and detours or works outside of the normal working hours. These works are subject to a separate approval process and are considered on an individual basis. Approvals may include the need to notify residents of the temporary change and in the case of works outside of normal working hours require subsequent approvals from the City’s Environmental Health Team and CEO.
 
**General Approvals
General approvals are granted to construction sites and long-term activities in the Station Precinct for daily activities such as general truck movements for deliveries and minor concrete pours. These works are only to be undertaken during normal working hours (7am – 7pm Monday -Saturday) and do not include works that will have a significant impact on access through/past the site area. General works are subject to a monthly approval process. 

Contact us

For more information, please contact the City.