Kensington Project Area

Background

Underground power is coming to the Kensington and Waterford Triangle areas through the Network Renewal Undergrounding Program Pilot (NRUPP) Tranche 2, bringing the last sections of the City’s power connections underground. The NRUPP replaces overhead power lines with underground power infrastructure in areas selected by Western Power. The Program is carried out by Western Power in partnership with local government.

Western Power is currently finalising the details for this project. Subject to council approval the project is expected to commence in the final quarter of 2025. 

What you can expect

We are working with Western Power to confirm the timelines and costs involved. Residents will be required to contribute to this upgrade and these costs will be outlineD in your 2025/26 Rates Notice. Exact cots for the project will be determined during our 2025/26 Annual Budget. Various payment options will be available.

You will receive another letter from us when the costs have been determined. This letter will also outline more details such as the possible impacts to your property and the expected timeline for the project.

We will host an information session for the community in partnership with Western Power. Experts from Western Power and the City will be in attendance, available to answer any questions and discuss the project in further detail.

Before construction begins and at the key stages of the project, Western Power’s appointed contractor will notify residents of the planned works.

Benefits of underground power

Underground power delivers a host of benefits which will enhance your neighbourhood. Some of the key benefits include:

  • Improved network safety and reliability
  • Improved streetscapes and visual amenity
  • Enhanced streetscapes with increased growth
  • Potential for increase in property values
  • Reduced vegetation trimming and maintenance costs
  • Brighter, more reliable LED streetlighting

Keeping you informed

We will provide further updates on this page as the project progresses. Affected ratepayers will soon be invited to an information session with Western Power and the project team to outline what you can expect and answer any questions or concerns you may have.

 

News Listings

April 2025
SouthPerthstreet

Underground power update - Kensington

News Update 10 April 2025

Western Power has provided an update on the estimated completion date for the Kensington underground power project.

Underground Power
Cardrivingdownatreelinedstreet

Underground power update for South Perth and Hurlingham

News Update 10 April 2025

Western Power has provided an update on the estimated completion date for the South Perth and Hurlingham underground power project.

Underground Power
December 2024

South Perth and Hurlingham underground power update

News Update 18 December 2024

The underground power project in the South Perth and Hurlingham areas is now scheduled for completion in June 2025.

Underground Power
UndergroundPower_0000s_0009_IMG_0324

Underground power update for Kensington

News Update 18 December 2024

Underground power is one step closer for the Kensington area, with Western Power finalising the design and issuing the project for tender.

Underground Power