Kensington Project Area

When viewed on the the website this widget will display a list of links to 'Anchor Destinations' that have been set within any 'Content block' on this page.

You should only use one per page and it should be above all 'Anchor Destinations' you have placed on the page.

Contents

Underground power is on its way to being delivered to the Kensington and Waterford Triangle areas through the Network Renewal Undergrounding Program Pilot (NRUPP) Tranche 2, bringing the last sections of the City’s power connections underground. 

Delivered by Western Power in partnership with the City, the Kensington Underground Power Project began in November 2025 and is expected to be completed by mid-2027. The NRUPP will connect more than 2,000 properties across Kensington, Waterford, Collier Reserve and remaining pockets of the City, remove 678 poles, replace 29 kilometres of overhead powerlines and install 552 new LED streetlights.

For project enquiries, please visit the Western Power website or call them on 13 10 87.

What to expect

The project area has been divided into eight zones, with work in all zones beginning in late 2025. 

Work is now well underway and Western Power’s appointed contractor will continue to notify residents at key stages of the project and before planned works begin.

 Kensington Project zone start date  estimated completion
Zone 1 End of 2025Mid-late 2026
Zone 2End of 2025Mid-late 2026
Zone 3End of 2025Late 2026
Zone 4End of 2025Early 2027
Zone 5End of 2025Early 2027
Zone 6End of 2025Mid 2027
Zone 7End of 2025Mid 2027
Zone 8End of 2025Mid 2027