Collier Project Area

Collier Project Zones
Collier Project | Start Date | Estimated Completion |
---|---|---|
Zone 1 | March 2021 | November 2021 |
Zone 2 | May 2021 | January 2022 |
Zone 3 | July/August 2021 | Feb/March 2022 |
Project Completed | March 2022 |
The Collier Underground Power Project was completed in March 2022, a few months ahead of schedule. Works in the area were staged in three zones (see map above) and proceeded in sequence by zone to minimise the impact on residents and enable the efficient reinstatement of verges.
The project was assessed and approved for implementation in 2017 within Round Six of the State Underground Power Program (SUPP), which had the objective to replace overhead power lines with underground power infrastructure. For more information about the SUPP and the process undertaken throughout the Collier project, please refer to the below documents and links.
State Underground Power Program FAQs
Underground Power Brochure – Collier
Western Power Underground Power website
Who to contact
For other project enquiries please visit the Western Power website or call them on 13 10 87.
News Listings
Underground Power - Community Information Session, Wednesday 25 May 2022
Property owners in the South Perth and Hurlingham area will be able to find out more about the City's next underground power project at a Community Information Session on Wednesday 25 May 2022.
Underground Power update
Underground power is one step closer in the South Perth and Hurlingham project areas.
State Underground Power works over Christmas
The Western Power State Underground Power Project (SUPP) contractor Genus will stop work on site for the Christmas break from Tuesday 21 December 2021 until Wednesday 5 January 2022.
Collier and Manning State Underground Power progress
The State Underground Power project in the Manning and Collier areas is progressing well with completion on schedule for mid 2022.