Collier Project Area

Map of the Zones in the Collier area

Collier Project Zones

Collier Project  Start Date Estimated Completion
Zone 1March 2021November 2021
Zone 2May 2021January 2022
Zone 3July/August 2021Feb/March 2022
Project Completed March 2022

The Collier Underground Power Project was completed in March 2022, a few months ahead of schedule. Works in the area were staged in three zones (see map above) and proceeded in sequence by zone to minimise the impact on residents and enable the efficient reinstatement of verges.

The project was assessed and approved for implementation in 2017 within Round Six of the State Underground Power Program (SUPP), which had the objective to replace overhead power lines with underground power infrastructure. For more information about the SUPP and the process undertaken throughout the Collier project, please refer to the below documents and links.

State Underground Power Program FAQs

Underground Power Brochure – Collier

Western Power Underground Power website

 

 

 

Who to contact

For other project enquiries please visit the Western Power website or call them on 13 10 87.

News Listings

April 2007
WardMap

Underground Power

Media Response 18 April 2007

Media enquiry regarding round three of the State Government's Underground Power Project.

Underground Power