South Perth Activity Centre Plan
On 21 December 2021, the Minister for Planning approved Scheme Amendment 61 (Amendment 61) to the City of South Perth Town Planning Scheme No. 6. The South Perth Activity Centre Plan (ACP) was also approved on 21 December 2021 by the Western Australian Planning Commission.
The South Perth ACP and Amendment 61 set out the City’s strategic vision and statutory planning requirements for development in the area between South Perth Peninsula, Richardson Park and Perth Zoo.
Amendment 61 and the South Perth ACP applies to all new development. A copy of approved Amendment 61 and the South Perth ACP is available for download via the document library.
The City’s vision for the South Perth Activity Centre was developed through the South Perth Peninsula Place & Design project in 2017:
A distinctive inner city activity centre, tourism destination and residential neighbourhood that is shaped by its connection to nature, unique assets, distinctive buildings, and future-forward approaches to sustainable living. Its lively centre and pedestrian friendly tree-lined streets connect locals and visitors to its diverse businesses, transport nodes and local heritage.
South Perth Activity Centre Plan project timeline
Milestone | Status |
---|---|
South Perth Peninsula Place & Design Report prepared | May 2017 |
Council resolves to prepare an Activity Centre Plan | June 2017 |
First draft Activity Centre Plan presented to Council. Resolved to further consider the draft plan, including built form and land use requirements. | October 2018 |
Council workshops to further consider the draft Activity Centre Plan | December 2018-February 2019 |
Draft Activity Centre Plan approved by Council for public advertising | 6 March 2019 |
Draft Activity Centre Plan approved by Western Australian Planning Commission (WAPC) and Environmental Protection Authority (EPA) for public advertising | April 2019 |
Draft Activity Centre Plan advertised for public comment | 14 May to 22 July 2019 |
Draft Activity Centre Plan modified as required in response to any feedback received | August-November 2019 |
Updated Activity Centre Plan approved by Council | 17 December 2019 |
Activity Centre Plan, including modifications, referred to the Western Australian Planning Commission (WAPC) for approval | January 2020 |
Amendment, including modifications, referred to the WAPC for approval and recommendation to the Minister for Planning | January 2020 |
Minister for Planning decides to either: approve the amendment; modify the amendment; or refuse to approve the amendment | January 2021 |
WAPC consideration of Activity Centre Plan for approval | March 2021 |
Resubmission of Activity Centre Plan to WAPC for approval | October 2021 |
Amendment forms part of the City of South Perth Town Planning Scheme 6 | December 2021 |