Manning Project Area
| Manning project | Start Date | Estimated Completion |
|---|---|---|
| Zone 1 | July/August 2021 | End of 2021 |
| Zone 2 | July/August 2021 | Early 2022 |
| Zone 3 | End of 2021 | Mid 2022 |
| Project Completion | Mid 2022 |
The Manning Underground Power Project was completed in September 2022. Works in the area were staged in three zones (see map above) and proceeded in sequence by zone to minimise the impact on residents and enable the efficient reinstatement of verges.
The project was assessed and approved for implementation in 2017 within Round Six of the State Underground Power Program (SUPP), which had the objective to replace overhead power lines with underground power infrastructure. For more information about the SUPP and the process undertaken throughout the Manning project, please refer to the below documents and links.
State Underground Power Program FAQs
Underground Power Brochure - Manning
Western Power Underground Power website
Who to contact
For other project enquiries please visit the Western Power website or call them on 13 10 87.