Civic Heart works
Civic Heart is a major development that will include two buildings of 39 and 22 storeys, and provide 309 residential dwellings, commercial and retail tenancies. The site is located at 1-3 Mends St in South Perth.
Construction commenced in January 2021 and is expected to take three years to complete. Residents with enquiries can email the builder directly at civicheart@hanssen.com.au.
DETAILS OF WORKS | WHO | DATE | TIME |
General construction activities contained on site. Northbound closure and truck access to/from Mends St. Southbound lane closure on Labouchere Rd southbound for general construction operations and deliveries. No right turn permitted
between Labouchere Rd and Bowman St and Labouchere Rd and Lyall St. | Hanssen Construction | Ongoing | 7am-6pm |
Construction site - general works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
1 Richardson St | South Perth | General construction operations contained on site. | EMCO Building | 4 - 9 Sept | 7am-6pm |
1-3 Mends St (Civic Heart) | South Perth | General construction activities contained on site. Northbound closure and truck access to/from Mends St. Southbound lane closure on Labouchere Rd southbound for general construction operations and deliveries. No right turn permitted between Labouchere Rd and Bowman St and Labouchere Rd and Lyall St. | Hanssen Construction | 4 - 9 Sept | 7am-6pm |
15 South Perth Esp | South Perth | General construction operations contained on site, some truck movements via South Perth Esp. | Giorgi | 4 - 9 Sept | 7am - 5pm |
17 Clydesdale St (Abode Apartments) | Como | General construction operations contained on site. | Jabiru Construction | 4 - 9 Sept | 7am - 6pm |
124 Lockhart Street | Como | General construction activities and truck movement on Lockhart St and Edgecumbe St. | Sale Alcock | 4 - 9 Sept | 7am - 5pm |
150 Robert St | Como | General construction activities and truck movements on Robert St. | Thomas Building | 4 - 9 Sept | 7am-5pm |
47 Clydesdale St | Como | General construction activities and truck movements on Clydesdale St. | Danmar Developments | 4 - 9 Sept | 7am-5pm |
69 South Perth Esp | South Perth | General construction activities and truck movements on Harper Tce and South Perth Esp. | Encon | 4 - 9 Sept | 7am-5pm |
8 Parker St | South Perth | General construction activities and truck movements on Parker St. | Built | 4 - 9 Sept | 7am-5pm |
Construction site - additional works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
1 Richardson Street | South Perth | Richardson Street and Melville Parade closed eastbound with detour for concrete pour | EMCO Building | 8 Sept |
Road works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
Mends St and Labouchere Rd | South Perth | Road closures and detours for Mends St between Labouchere Rd and Mill Point Rd. To facilitate road upgrade works. | BOS Civil | 4 Sept - 11 Nov | 7am - 6pm |
Long term works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
6 Hopetoun St | South Perth | General construction activities and truck movements. | GreenbuiltWA | Sept-Dec 23 | 7am-5pm |
Services works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
None notified |
Short-term low-impact works/ events
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
2 Harper Tce | South Perth | Footpath closure and detour for facade works on building along Harper Terrace and Mill Point Road. | RE Asset Logistics / ATM | 4-28 Sept | 7am - 5pm Mon-Thurs only |
2 Harper Tce | South Perth | Southbound road closure for façade works on building along Harper Tce and Mill Point Road | RE Asset Logistics / ATM | 5-7 Sept; 13-14 Sept & 20-21 Sept | 7am - 5pm |
Upcoming works / events (works may not yet be approved; dates and times may be subject to change)
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
1-3 Mends St (Civic Heart) | South Perth | Southbound closure and northbound lane closure of Labouchere Road for tower crane removal | Hanssen Construction | 16-17 Sept or 23-24 Sept | 4am Sat - 9pm Sun |
To report a safety or accident hazard please contact the City or report the incident online via the City's
Make a Request page.
Details of other road works in the City can be found on the
construction and maintenance work page of the website.
* Upcoming works/events may not yet be approved. Dates and times may be subject to change.