South Perth Station Precinct works: 28 January - 3 February 2019

Public Notice 29 January 2019
Connect South Road Works SPSP Traffic

Approved works within the South Perth Station Precinct for 28 January - 3 February 2019:

LOCATION DETAILS OF WORKS WHO DATE TIME
Construction site - abnormal works*
South Perth Esplanade
Installation of temporary fencing along South Perth Esplanade surrounding the Connect South construction site.
Selected parking bays on South Perth Esplanade will be closed to facilitate the installation.
Footpath closures will be in place.
City of South Perth  4 Feb 7am-4pm 
South Perth Esplanade
Installation of an access ramp and island cut through on both the eastern side and western side of South Perth Esplanade. Traffic management will be in place on South Perth Esplanade during work hours.
City of South Perth 
5 Feb 9am-3pm
21 Mends Street (Harper Terrace) Lane closure and traffic control on Harper Terrace for building façade works. Quest Apartments / Pindan 1-2 Feb 7am-5pm
21 Mends Street (Harper Terrace) Mobile crane lifts, under traffic control, road closure of central Harper Terrace for window glazing installation. Quest Apartments / Pindan 29-31 Jan 7am-3pm
Construction site - general approvals**

39 Mends Street (Echelon)

Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours.

Giorgi

29 Jan-2 Feb

7am-5pm

21 Mends Street (Harper Terrace)

General construction operations contained on site.

Quest Apartments/Pindan

29 Jan-2 Feb

7am-5pm

26 Charles Street General truck movements on Charles Street, footpath closure and detour for construction operations. Cockram Constructions
 
29 Jan-2 Feb 7am-5pm
Short term low impact works/events
South Perth Esplanade Testing of Autonomous bus on South Perth Esplanade, Mill Point Close and Mill Point Road. RAC 29 Jan-3 Feb 9am-5pm
Upcoming works
Connect South Mobilisation and delivery of site facilities, machinery and material. Delivery trucks to be entering/exiting the site.
City of South Perth  4-8 Feb 7am-4pm
Connect South
Demolition works to commence. MG to demolish and dispose of the pavilion, brick paving, vegetation, benches, etc.
General truck movements in and out of the site will be occurring.
Footpath closures will be in place.
Minor traffic management in place on South Perth Esplanade to facilitate the work.
Selected parking bays on South Perth Esplanade will be closed.
City of South Perth 
5-8 Feb  7am-4pm 
11 Melville Parade Subject to final approvals
Construction activities with truck access via Melville Parade.
Thomas Contracting TBC TBC
Mill Point Rd / Labouchere Rd Subject to approvals
Installation of fibre optic cable
LADCOM Design TBC TBC
Labouchere Rd / Charles St Subject to approvals
Installation of conduit and pits
TPG Telecom (PipeNetworks) TBC TBC
South Perth Esplanade
Testing of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road.  RAC  26 Feb 9am-5pm

To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.

Details of other road works in the City can be found on the construction and maintenance work page of the website.

*Abnormal works
Abnormal works are one off activities that require significant truck movements, obstructions to movement such as road closures and detours or works outside of the normal working hours. These works are subject to a separate approval process and are considered on an individual basis. Approvals may include the need to notify residents of the temporary change and in the case of works outside of normal working hours require subsequent approvals from the City’s Environmental Health Team and CEO.
 
**General Approvals
General approvals are granted to construction sites and long-term activities in the Station Precinct for daily activities such as general truck movements for deliveries and minor concrete pours. These works are only to be undertaken during normal working hours (7am – 7pm Monday -Saturday) and do not include works that will have a significant impact on access through/past the site area. General works are subject to a monthly approval process. 