South Perth Station Precinct works: 24 December 2018 to 6 January 2019
Approved works within the South Perth Station Precinct for 24 December 2018 to 6 January 2019:
LOCATION | DETAILS OF WORKS | WHO | DATE | TIME |
Construction site - abnormal works* | ||||
26 Charles Street | Concrete pour - traffic control and reversible flow. | Cockram Constructions | 28 Dec | 7am-5pm |
Construction site - general approvals** | ||||
39 Mends Street (Echelon) |
Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours. |
Giorgi |
24 Dec - 5 Jan (exc Public Holidays) |
7am-5pm |
21 Mends Street (Harper Terrace) |
Mobilisation of minor materials and equipment to site for plumbing, electrical & mechanical works, |
Quest Apartments/Pindan |
24 Dec - 5 Jan (exc Public Holidays) |
7am-5pm |
5 Harper Terrace (Reva) |
Hanssen |
|
7 |
|
26 Charles Street | General truck movements on Charles Street, footpath closure and detour for construction operations. | Cockram Constructions |
24 Dec - 5 Jan (exc Public Holidays) | 7am-5pm |
Short term low impact works/events | ||||
South Perth Esplanade | Testing of Autonomous bus on South Perth Esplanade, Mill Point Close and Mill Point Road. | RAC | 4 January | 8.30am-5pm |
Upcoming works | ||||
11 Melville Parade | Subject to final approvals Construction activities with truck access via Melville Parade. |
Thomas Contracting | TBC | TBC |
Mill Point Rd / Labouchere Rd | Subject to approvals Installation of fibre optic cable |
LADCOM Design | TBC | TBC |
Labouchere Rd / Charles St | Subject to approvals Installation of conduit and pits |
TPG Telecom (PipeNetworks) | TBC | TBC |
South Perth Esplanade | Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road. | RAC | 8-13 Jan | 9am-5pm |
26 Charles Street | Subject to approvals Tower crane installation, half road closure with traffic controllers on site to manage movements. |
Cockram Constructions | 11-12 Jan | 7am-5pm |
26 Charles Street | Subject to approvals Concrete panel lifts with traffic control and reversible flow. |
Cockram Constructions | 14-16 Jan | 7am-5pm |
To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.
Details of other road works in the City can be found on the construction and maintenance work page of the website.
*Abnormal works
Abnormal works are one off activities that require significant truck movements, obstructions to movement such as road closures and detours or works outside of the normal working hours. These works are subject to a separate approval process and are considered on an individual basis. Approvals may include the need to notify residents of the temporary change and in the case of works outside of normal working hours require subsequent approvals from the City’s Environmental Health Team and CEO.
**General Approvals
General approvals are granted to construction sites and long-term activities in the Station Precinct for daily activities such as general truck movements for deliveries and minor concrete pours. These works are only to be undertaken during normal working hours (7am – 7pm Monday -Saturday) and do not include works that will have a significant impact on access through/past the site area. General works are subject to a monthly approval process.
Contact us
- Phone 9474 0777