South Perth Station Precinct works update: week commencing 10 December
Approved works within the South Perth Station Precinct for the week commencing 10 December 2018:
LOCATION | DETAILS OF WORKS | WHO | DATE | TIME |
---|---|---|---|---|
LOCATION | DETAILS OF WORKSConstruction site - abnormal works* | WHO | DATE | TIME |
LOCATION21 Mends Street (Harper Terrace) | DETAILS OF WORKSSouthbound road closure on Harper Terrace for building façade works. | WHOQuest Apartments/Pindan | DATE10-14 Dec | TIME7am-4pm |
LOCATION21 Mends Street (Harper Terrace) | DETAILS OF WORKSMobile crane lifts, under traffic control, road closure of central Harper Tce during crane operations. | WHOQuest Apartments/Pindan | DATE12 Dec | TIME7am-3pm |
LOCATION1 Richardson St | DETAILS OF WORKSStop/slow control on Richardson Street and parking closure for the relocation of site hoarding. | WHOBroad Construction | DATE10 Dec | TIME7am-3pm |
LOCATIONRichardson St | DETAILS OF WORKS Road rehabilitation works with half road closure with stop/slow control. | WHOCity of South Perth | DATE11-14 Dec | TIME7am-5pm |
LOCATION21 Mends Street (Harper Terrace) | DETAILS OF WORKS Mobile crane lifts, under traffic control, road closure of Harper Terrace between Aurelia and Quest Apartments during crane operations. | WHOQuest Apartments/Pindan | DATE14 Dec | TIME7am-3pm |
LOCATION | DETAILS OF WORKSConstruction site - general approvals** | WHO | DATE | TIME |
LOCATION
39 Mends Street (Echelon) |
DETAILS OF WORKS
Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours. |
WHO
Giorgi |
DATE
10-15 Dec |
TIME
7am-5pm |
LOCATION
21 Mends Street (Harper Terrace) |
DETAILS OF WORKS
Mobilisation of minor materials and equipment to site for plumbing, electrical & mechanical works, |
WHO
Quest Apartments/Pindan |
DATE10-15 Dec |
TIME
7am-5pm |
LOCATION
5 Harper Terrace (Reva) |
DETAILS OF WORKS
Unloading of trucks within work zone area adjacent to site, with Harper Terrace open to traffic. |
WHO
Hanssen |
DATE
10-15 Dec |
TIME
7am-5pm |
LOCATION26 Charles Street | DETAILS OF WORKSGeneral truck movements on Charles Street, footpath closure and detour for construction operations. | WHOCockram Constructions |
DATE10-15 Dec | TIME7am-5pm |
LOCATION | DETAILS OF WORKS
Other works |
WHO | DATE | TIME |
LOCATION
South Perth Esplanade |
DETAILS OF WORKS
Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road. |
WHO
RAC |
DATE
11-16 Dec |
TIME
9am-5pm |
LOCATION | DETAILS OF WORKS
Upcoming works |
WHO | DATE | TIME |
LOCATIONMill Point Rd / Labouchere Rd |
DETAILS OF WORKSSubject to approvals. Installation of fibre optic cable. |
WHOLADCOM Design | DATETBC | TIMETBC |
LOCATION11 Melville Pde | DETAILS OF WORKSSubject to final approvals. Construction activities with truck access via Melville Parade. |
WHOThomas Contracting | DATETBC | TIMETBC |
LOCATIONLabouchere Rd/Charles St | DETAILS OF WORKS Subject to approvals. Installation of conduit and pits. |
WHOTPG Telecom (PipeNetworks) | DATETBC | TIMETBC |
LOCATIONRichardson Street | DETAILS OF WORKS Road rehabilitation works with road closure for resurfacing works. | WHOCity of South Perth | DATE18-19 Dec | TIME7am-5pm |
LOCATION39 Mends Street (Echelon) & South Perth Esplanade | DETAILS OF WORKSSubject to final approval. Half road closure and traffic control for crane removal. | WHOGiorgi | DATE19-23 Dec | TIME7am-5.30pm |
To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.
Details of other road works in the City can be found on the construction and maintenance work page of the website.
*Abnormal works
Abnormal works are one off activities that require significant truck movements, obstructions to movement such as road closures and detours or works outside of the normal working hours. These works are subject to a separate approval process and are considered on an individual basis. Approvals may include the need to notify residents of the temporary change and in the case of works outside of normal working hours require subsequent approvals from the City’s Environmental Health Team and CEO.
**General Approvals
General approvals are granted to construction sites and long-term activities in the Station Precinct for daily activities such as general truck movements for deliveries and minor concrete pours. These works are only to be undertaken during normal working hours (7am – 7pm Monday -Saturday) and do not include works that will have a significant impact on access through/past the site area. General works are subject to a monthly approval process.