South Perth Station Precinct works update: week commencing 19 November

Public Notice 19 November 2018
Maintenance Works Road Works SPSP Traffic

Approved works within the South Perth Station Precinct for the week commencing 19November 2018:

LOCATION DETAILS OF WORKS WHO DATE TIME
Construction site - abnormal works*
21 Mends Street Footpath closure on west side of Mends Street with traffic controllers to assist pedestrians for Glass Canopy installation. Quest Apartments/Pindan
19 Nov 7am -3pm
21 Mends Street (Harper Terrace)  Subject to approvals. Mobile crane lifts, under traffic control, access to be maintained and managed on Harper Terrace at all times.  Quest Apartments/Pindan  21 and 23 Nov  7am-3pm 
Construction site - general approvals**

39 Mends Street (Echelon)

Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours.

Giorgi

19-24 Nov

7am-5pm

21 Mends Street (Harper Terrace)

Mobilisation of minor materials and equipment to site for Plumbing, Electrical & Mechanical Works,
Delivery and Installation of Scaffold to Site, including delivery trucks entering / exiting the site.
Delivery and Installation of Structural Steel, Window, Cabinetry, , Tiles and Roof Sheeting.

Quest Apartments/Pindan

19-24 Nov

7am-5pm

5 Harper Terrace (Reva)

General truck movements on Harper Terrace, Minor concrete pours

Hanssen

19-24 Nov

7am-5pm

   Services works      
Ferry St / Mill Point Rd (North) Lane closures and traffic control for the installation of LV power cable.
Complete Cabling 19-23 Nov 7am-5pm

Other works

South Perth Esplanade

Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road.

RAC

20-25 Nov

9am-5pm

Upcoming works

Ferry St/Mill Point Rd / Harper Tce
Subject to final approval. Lane and road closures for pillar energisation.  Complete Cabling 28 Nov 7am-5pm
26 Charles St  Subject to approvals. General truck movements on Charles Street for the commencement of construction operations.  Cockram Constructions  Commencing 3 December  7am-5pm 
Mill Point Rd / Labouchere Rd
Subject to approvals. Installation of fibre optic cable.
 
LADCOM Design TBC TBC
Labouchere Rd / Charles St
Subject to approvals. Installation of conduit and pits. TPG Telecom (Pipe Networks)
TBC TBC
Richardson Street  Subject to approvals. Half road closure with stop/slow control.  City of South Perth  12-18 Dec  7am-5pm 
Richardson Street   Subject to approvals. Road closure for resurfacing works.  City of South Perth  19-20 Dec  7am-5pm 

To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.

Details of other road works in the City can be found on the construction and maintenance work page of the website.

*Abnormal works
Abnormal works are one off activities that require significant truck movements, obstructions to movement such as road closures and detours or works outside of the normal working hours. These works are subject to a separate approval process and are considered on an individual basis. Approvals may include the need to notify residents of the temporary change and in the case of works outside of normal working hours require subsequent approvals from the City’s Environmental Health Team and CEO.
 
**General Approvals
General approvals are granted to construction sites and long-term activities in the Station Precinct for daily activities such as general truck movements for deliveries and minor concrete pours. These works are only to be undertaken during normal working hours (7am – 7pm Monday -Saturday) and do not include works that will have a significant impact on access through/past the site area. General works are subject to a monthly approval process. 

Contact us

For more information, please contact the City.