South Perth Station Precinct works update: week commencing 29 October

Public Notice 29 October 2018
Maintenance Works Road Works SPSP Traffic

Approved works within the South Perth Station Precinct for the week commencing 29 October 2018:

LOCATION DETAILS OF WORKS WHO DATE TIME
LOCATION DETAILS OF WORKSConstruction site - abnormal works* WHO DATE TIME
LOCATION11 Melville Parade DETAILS OF WORKSSubject to final approvals
Demolition works with truck access via Melville Parade.
WHOThomas Contracting
DATE29 Oct-16 Nov TIME7am - 5.30pm (M-F)
7am - 3pm (Sat)
LOCATION5 Harper Terrace (Reva)
DETAILS OF WORKSRoad closure with limited access on Harper Terrace for Crane Demobilisation  WHOHanssen
DATE1 November TIME6.30am-5pm
LOCATION DETAILS OF WORKSConstruction site - general approvals** WHO DATE TIME
LOCATION

39 Mends Street (Echelon)

DETAILS OF WORKS

Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours.

WHO

Giorgi

DATE

29-3 Nov

TIME

7am-5pm

LOCATION

21 Mends Street (Harper Terrace)

DETAILS OF WORKS

Concrete pouring to easement extension, including concrete trucks entering/exiting the site,
mobilisation of minor materials and equipment to site for plumbing, electrical and mechanical works.
Delivery and installation of scaffold to site, including delivery trucks entering/exiting the site.
Delivery and installation of structural steel, window, cabinetry and roof sheeting.

WHO

Quest Apartments/Pindan

DATE29-3 Nov
TIME

7am-5pm

LOCATION

5 Harper Terrace (Reva)

DETAILS OF WORKS

General truck movements on Harper Terrace, remedial work on sinkhole, road and diaphragm wall, minor concrete pours.

WHO

Hanssen

DATE

29-3 Nov

TIME

7am-5pm

LOCATION DETAILS OF WORKS

Other works

WHO DATE TIME
LOCATION

South Perth Esplanade

DETAILS OF WORKS

Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road.

WHO

RAC

DATE

30-4 Nov

TIME

9am-5pm

LOCATION  DETAILS OF WORKSShort term low impact works/ events
WHO  DATE  TIME 
LOCATIONSouth Perth Esplanade
DETAILS OF WORKSOperation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road.
WHORAC DATE31 Oct TIME6am-4.30pm
LOCATIONLabouchere Rd / Mill Point Rd
DETAILS OF WORKSBanner Changeover - Short term lane closures Labouchere Rd and Mill Point Rd WHOCity of South Perth DATE1 Nov TIME10am-2pm
LOCATION DETAILS OF WORKS

Upcoming works

WHO DATE TIME
LOCATION

Ferry St/Mill Point Rd / Harper Tce

DETAILS OF WORKS

Subject to approvals
Installation of LV power cable

WHO

Complete Cabling

DATE

TBC

TIMETBC            
LOCATIONMill Point Rd / Labouchere Rd
DETAILS OF WORKSSubject to approvals
Installation of fibre optic cable
 
WHOLADCOM Design DATETBC TIMETBC
LOCATIONLabouchere Rd / Charles St
DETAILS OF WORKSSubject to approvals
Installation of conduit and pits
WHOTPG Telecom (Pipe Networks)
DATETBC TIMETBC

To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.

Details of other road works in the City can be found on the construction and maintenance work page of the website.

*Abnormal works
Abnormal works are one off activities that require significant truck movements, obstructions to movement such as road closures and detours or works outside of the normal working hours. These works are subject to a separate approval process and are considered on an individual basis. Approvals may include the need to notify residents of the temporary change and in the case of works outside of normal working hours require subsequent approvals from the City’s Environmental Health Team and CEO.
 
**General Approvals
General approvals are granted to construction sites and long-term activities in the Station Precinct for daily activities such as general truck movements for deliveries and minor concrete pours. These works are only to be undertaken during normal working hours (7am – 7pm Monday -Saturday) and do not include works that will have a significant impact on access through/past the site area. General works are subject to a monthly approval process. 

Contact us

For more information, please contact the City or Make a Request online.
  • Phone 9474 0777