South Perth Station Precinct works update: week commencing 1 October

Public Notice 1 October 2018
Maintenance Works Road Works SPSP Traffic

Approved works within the South Perth Station Precinct for the week commencing 1 October 2018:

LOCATION DETAILS OF WORKS WHO DATE TIME
Construction site - abnormal works*
Mends Street (MPR - SPE) Closure of Mends Street (Mill Point Road - South Perth Esplanade) to facilitate crane operations. General / Workforce Road Services 3 Oct 9pm-6am
Construction site - general approvals**

39 Mends Street (Echelon)

Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours.

Giorgi

1-6 Oct

7am-5pm

21 Mends Street (Harper Terrace)

Concrete pouring to easement extension, including concrete trucks entering/exiting the site,
mobilisation of minor materials and equipment to site for plumbing, electrical and mechanical works.
Delivery and installation of scaffold to site, including delivery trucks entering/exiting the site.
Delivery and installation of structural steel, window, cabinetry and roof sheeting.

Quest Apartments/Pindan

1-6 Oct

7am-5pm

5 Harper Terrace (Reva)

General truck movements on Harper Terrace, remedial work on sinkhole, road and diaphragm wall, minor concrete pours.

Hanssen

1-6 Oct

7am-5pm

Other works

South Perth Esplanade

Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road.

RAC

2-7 Oct

9am-5pm

Upcoming works

Lyall Street & Labouchere Road

Delivery of modular building display suite

Fleetwood

TBC

TBC            

To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.

Details of other road works in the City can be found on the construction and maintenance work page of the website.

*Abnormal works
Abnormal works are one off activities that require significant truck movements, obstructions to movement such as road closures and detours or works outside of the normal working hours. These works are subject to a separate approval process and are considered on an individual basis. Approvals may include the need to notify residents of the temporary change and in the case of works outside of normal working hours require subsequent approvals from the City’s Environmental Health Team and CEO.
 
**General Approvals
General approvals are granted to construction sites and long-term activities in the Station Precinct for daily activities such as general truck movements for deliveries and minor concrete pours. These works are only to be undertaken during normal working hours (7am – 7pm Monday -Saturday) and do not include works that will have a significant impact on access through/past the site area. General works are subject to a monthly approval process. 