South Perth Station Precinct works update: week commencing 11 June 2018
Approved works within the South Perth Station Precinct for the week commencing 11 June 2018:
LOCATION | DETAILS OF WORKS | WHO | DATE | TIME |
Construction site - abnormal works* | ||||
5 Harper Terrace (Reva) |
Harper Terrace half road closure with reversible flow managed by traffic control for internal concrete pour. |
Hanssen | 14-15 June | 7am-12pm |
Construction site - general approvals** | ||||
39 Mends Street (Echelon) |
Dewatering, shotcreting piled walls, excavation, formwork and concrete pours. Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours. | Giorgi |
11-16 June | 7am-5pm |
21 Mends Street (Harper Terrace) | Reinforcement steel deliveries and steel fixing, including delivery truck entering/exiting the site, concrete pouring to slabs/columns/walls, including concrete trucks entering/ exiting the site. Mobilisation of minor materials and equipment to site for plumbing, electrical and mechanical works. Delivery and installation of formwork and scaffold to site, including delivery trucks entering/exiting the site. Delivery and installation of precast concrete walls. Delivery and installation of AFS. |
Quest Apartments/Pindan | 11-16 June | 7am-5pm |
35 Mends Street | Mobilisation of minor materials and equipment to site for plumbing, electrical & formworker, delivery and installation of formwork to site, including delivery trucks entering/exiting the site delivery and installation of block work. | Pindan | 11-16 June | 7am-5pm |
1 Stone Street | Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street. |
Danmar Developments |
11-16 June |
7am-5pm |
5 Harper Terrace (Reva) | General truck movements on Harper Terrace, Remedial work on sinkhole, road & diaphragm wall. Minor concrete pours. | Hanssen | 11-16 June | 7am-5pm |
26 Charles Street | Bulk earthworks and reduced levels. Some head works for contiguous piles. Preparation for some concrete formwork and reinforcement. |
Pindan | 11-16 June | 7am-5pm |
Other works | ||||
South Perth Esplanade | Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road. | RAC | 17 June | 9am-5pm |
Mends Street (Mill Point Rd to South Perth Esplanade) | Closure of Mends Street for the Mends Street Community Market (Sunday weekly). | Mend Street Traders/City of South Perth | 17 June | 5am-2pm |
Upcoming works | ||||
Mends Street (Mill Point Road - South Perth Esplanade) | Closure of Mends Street for the Mends Street Markets (Sunday Weekly) | Mends Street Traders / CoSP |
17 June | 5am-2pm |
South Perth Esplanade | Operation of Autonomous bus on South Perth Esplanade, Mill Point Close and Mill Point Road. | RAC | 25 June | 9am-1pm |
South Perth Esplanade | Subject to approvals. Operation of Autonomous bus on South Perth Esplanade, Mill Point Close and Mill Point Road. |
RAC |
3 July & 24 July |
9am-5pm |
South Perth Esplanade | Subject to approvals. Operation of Autonomous bus on South Perth Esplanade, Mill Point Close and Mill Point Road. |
RAC | 13 July & 31 August | 9am-1pm |
To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.
Details of other road works in the City can be found on the construction and maintenance work page of the website.
*Abnormal works
Abnormal works are one off activities that require significant truck movements, obstructions to movement such as road closures and detours or works outside of the normal working hours. These works are subject to a separate approval process and are considered on an individual basis. Approvals may include the need to notify residents of the temporary change and in the case of works outside of normal working hours require subsequent approvals from the City’s Environmental Health Team and CEO.
**General Approvals
General approvals are granted to construction sites and long-term activities in the Station Precinct for daily activities such as general truck movements for deliveries and minor concrete pours. These works are only to be undertaken during normal working hours (7am – 7pm Monday -Saturday) and do not include works that will have a significant impact on access through/past the site area. General works are subject to a monthly approval process.
Contact us
- Phone 9474 0777