Approved works within the South Perth Station Precinct for the week commencing 26 March 2018:
LOCATION | DETAILS OF WORKS | WHO | DATE | TIME |
Construction site - abnormal works | ||||
21-23 Mends Street (Harper Terrace) | Early morning start concrete pour with truck access from Mill Point Road and South Perth Esplanade. | Quest Apartments/Pindan | 24 March | 4.30am-5pm |
39 Mends Street (Echelon) | Subject to final approvals Early morning start concrete pour, truck access via South Perth Esplanade reversing into site. |
Giorgi | 26-29 March | 5.30am-5pm |
Construction site - general approvals | ||||
39 Mends Street (Echelon) |
Dewatering, Shotcreting piled walls, excavation, formwork and concrete pours. Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours. | Giorgi |
26-29 March | 7am-5pm |
21 Mends Street (Harper Terrace) | Implementation of on street loading area on Harper Terrace contained within the work site boundary. Steel and bubbledeck delivery, resulting in truck movements impacting on Harper Terrace. Delivery and installation of precast panels and AFS. |
Quest Apartments/Pindan | 26-29 March | 7am-5pm |
1 Stone Street | Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street. |
Danmar Developments |
26-29 March |
7am-5pm |
5 Harper Terrace (Reva) | General truck movements on Harper Terrace for dirt removal and minor concrete pours | Hanssen | 26-29 March | 7am-5pm |
96 Mill Point Road (Aurelia) | Footpath works on Harper Terrace. Harper Terrace closed to general traffic at northern site boundary. |
Hanssen | 26-29 March |
7am-5pm |
26 Charles Street | Bulk earthworks and reduced levels. Some head works for contiguous piles. Preparation for some concrete formwork and reinforcement. |
Pindan | 26-29 March | 7am-5pm |
Other works | ||||
South Perth Esplanade | Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road. | RAC | 27-29 March | 9am-5pm |
Upcoming works | ||||
Mends Street (Mill Point Rd to South Perth Esplanade) |
Closure of Mends Street for the Mends Street Community Market. |
Mend Street Traders/CoSP |
7April | 5am-2pm |
To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.
Details of other road works in the City can be found on the construction and maintenance work page of the website.
Contact us
- Phone 9474 0777