Weekly approved works 24 - 30 June 2024
Approved works in the City of South Perth for 24 - 30 June 2024.
Civic Heart works
Civic Heart is a major development that will include two buildings of 39 and 22 storeys, and provide 309 residential dwellings, commercial and retail tenancies. The site is located at 1-3 Mends Street in South Perth.
Construction commenced in January 2021 and is expected to take three years to complete. Residents with enquiries can email the builder directly at civicheart@hanssen.com.au.
DETAILS OF WORKS | WHO | DATE | TIME |
General construction activities contained on site. Northbound closure and truck access to/from Mends Street. Southbound lane closure on Labouchere Road southbound for general construction operations and deliveries. No right turn permitted
between Labouchere Road and Bowman Street and Labouchere Road and Lyall Street. | Hanssen Construction | Ongoing | 7am-6pm |
Construction site - general works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
1 Richardson Street | South Perth | General construction operations contained on site. | EMCO Building | 24 - 29 June | 7am-6pm |
1-3 Mends Street (Civic Heart) | South Perth | General construction activities contained on site. Northbound closure and truck access to/from Mends Street. Southbound lane closure on Labouchere Road southbound for general construction operations and deliveries. No right turns permitted between Labouchere Road and Bowman Street and Labouchere Road and Lyall Street | Hanssen Construction | 24 - 29 June | 7am-6pm |
15 South Perth Esplanade | South Perth | General construction operations contained on site, some truck movements via South Perth Esplanade | Giorgi | 24 - 29 June | 7am-5pm |
150 Robert Street | Como | General construction activities and truck movements on Robert Street | Thomas Building | 24 - 29 June | 7am-5pm |
47 Clydesdale Street (Como) | Como | General construction activities and truck movements on Clydesdale Street | Danmar Developments | 24 - 29 June | 7am-5pm |
69 South Perth Esplanade | South Perth | General construction activities and truck movements on Harper Terrace and South Perth Esplanade | Encon | 24 - 29 June | 7am-5pm |
74 Mill Point Road (Lumiere) | South Perth | General construction activities and truck movements on Mill Point Road | Edge Construction | 24 - 29 June | 7am-7pm |
Construction site - additional works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
69 South Perth Esplanade | South Perth | Full road closure of Harper Terrace to facilitate crane lifting operations | Encon | 28 June | 6.30am - 5pm |
Road works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
Duckett Drive, Cloister Avenue to Conochie Crescent | Manning | Infrastructure civil/Asphalt works | City of South Perth/Asphaltech | 24 - 28 June | 7am-5pm |
Long term works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
None notified |
Services works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
None notified |
Short-term low-impact works/ events
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
72 Melville Pde, South Perth (from Charles St) | South Perth | Out of hours crane lift/EWP operations for the delivery, maintenance and removal of telecommunications infrastructure | Workforce Road Services | 30 June 2024 | 7am - 7pm |
Upcoming works / events (works may not yet be approved; dates and times may be subject to change)
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
72 Melville Parade | South Perth | Road closure of Charles Street at Melville Parade for telecommunications work | General Crane Services | 30 Jun & 7 Jul | 7am - 7pm |
17 Clydesdale Street (Abode Apartments) | Como | Awaiting re-approval General construction operations contained on site | Jabiru Construction | 24 - 29 June | 7am-6pm |
1 Richardson Street | South Perth | Subject to approval Road closure of Richardson Street (Labouchere Road-Charles Street) for tower crane removal | EMCO Building | 22 - 26 July | 7am-6pm |
To report a safety or accident hazard please contact the City or report the incident online via the City's
Make a Request page.
Details of other road works in the City can be found on the
construction and maintenance work page of the website.
* Upcoming works/events may not yet be approved. Dates and times may be subject to change.
Media contact
- Phone 9474 0777
- Email media@southperth.wa.gov.au