Weekly approved works 6 - 12 May 2024
Approved works in the City of South Perth for 6 - 12 May 2024.
Civic Heart works
Civic Heart is a major development that will include two buildings of 39 and 22 storeys, and provide 309 residential dwellings, commercial and retail tenancies. The site is located at 1-3 Mends St in South Perth.
Construction commenced in January 2021 and is expected to take three years to complete. Residents with enquiries can email the builder directly at civicheart@hanssen.com.au.
DETAILS OF WORKS | WHO | DATE | TIME |
---|---|---|---|
DETAILS OF WORKSGeneral construction activities contained on site. Northbound closure and truck access to/from Mends St. Southbound lane closure on Labouchere Rd southbound for general construction operations and deliveries. No right turn permitted
between Labouchere Rd and Bowman Street and Labouchere Road and Lyall Street. | WHOHanssen Construction | DATEOngoing | TIME7am-6pm |
Construction site - general works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
---|---|---|---|---|---|
LOCATION1 Richardson Street | SUBURBSouth Perth | DETAILS OF WORKSGeneral construction operations contained on site. | WHOEMCO Building | DATE6-11 May | TIME7am - 6pm |
LOCATION1-3 Mends Street (Civic Heart) | SUBURBSouth Perth | DETAILS OF WORKSGeneral construction activities contained on site. Northbound closure and truck access to/from Mends Street. Southbound lane closure on Labouchere Road southbound for general construction operations and deliveries. No right turns permitted between Labouchere Road and Bowman Street and Labouchere Road and Lyall Street. | WHOHanssen Construction | DATE6-11 May | TIME7am - 6pm |
LOCATION15 South Perth Esplanade | SUBURBSouth Perth | DETAILS OF WORKSGeneral construction operations contained on site, some truck movements via South Perth Esplanade. | WHOGiorgi | DATE6-11 May | TIME7am - 5pm |
LOCATION17 Clydesdale Street (Abode Apartments) | SUBURBComo | DETAILS OF WORKSGeneral construction operations contained on site. | WHOJabiru Construction | DATE6-11 May | TIME7am - 6pm |
LOCATION150 Robert St | SUBURBComo | DETAILS OF WORKSGeneral construction activities and truck movements on Robert Street. | WHOThomas Building | DATE6-11 May | TIME7am - 5pm |
LOCATION47 Clydesdale Street (Como) | SUBURBComo | DETAILS OF WORKSGeneral construction activities and truck movements on Clydesdale Street. | WHODanmar Developments | DATE6-11 May | TIME7am - 5pm |
LOCATION69 South Perth Esplanade | SUBURBSouth Perth | DETAILS OF WORKSGeneral construction activities and truck movements on Harper Terrace and South Perth Esplanade. | WHOEncon | DATE6-11 May | TIME7am - 5pm |
LOCATION74 Mill Point Road (Lumiere) | SUBURBSouth Perth | DETAILS OF WORKSGeneral construction activities and truck movements on Mill Point Road. | WHOEdge Construction | DATE6-11 May | TIME7am - 7pm |
Construction site - additional works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
---|---|---|---|---|---|
LOCATION1-3 Mends Street (Civic Heart) | SUBURBSouth Perth | DETAILS OF WORKSLabouchere Rd southbound closure at Mill Point Rd for tower crane removal from site | WHOHanssen Construction | DATE4-5 May | TIME4am Sat - 9pm Sun |
LOCATION1 Richardson Street | SUBURBSouth Perth | DETAILS OF WORKSRichardson Street and Melville Parade closed eastbound with detour for concrete pour. | WHOEMCO Building | DATE7 & 9 May | TIME7am - 5pm |
Road works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
---|---|---|---|---|---|
LOCATION South Perth Esplanade | SUBURBSouth Perth | DETAILS OF WORKSRoad closures on South Perth Esplanade between Mends Street and Queen Street to facilitate road resurfacing. | WHOWCP / City of South Perth | DATE9-10 May | TIME9am - 3pm |
LOCATION Labouchere Road | SUBURBSouth Perth | DETAILS OF WORKSLane closures southbound on Labouchere Road between Mill Point Road and Mends Street. To facilitate road upgrade works. | WHOBOS Civil | DATE6-25 May | TIME7am - 6pm |
LOCATION Labouchere Road | SUBURBSouth Perth | DETAILS OF WORKSLane closures both northbound and southbound on Labouchere Road between Mill Point Road and Mends Street. To facilitate road upgrade works. | WHOBOS Civil | DATE6-25 May | TIME9am - 2pm |
Long term works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
---|---|---|---|---|---|
LOCATIONNone Notified | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
Services works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
---|---|---|---|---|---|
LOCATION72 Melville Parade | SUBURBSouth Perth | DETAILS OF WORKSRoad closure of Charles Street at Melville Parade for telecommunications work. | WHOGeneral Crane Services | DATE5, 12 & 19 May | TIME7am - 7pm |
Short-term low-impact works/ events
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
---|---|---|---|---|---|
LOCATION None notified | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
Upcoming works / events (works may not yet be approved; dates and times may be subject to change)
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
---|---|---|---|---|---|
LOCATIONLabouchere Road | SUBURBSouth Perth | DETAILS OF WORKSSubject to final approval Northbound lane closures on Labouchere Road between Mill Point Road and Mends Street. To facilitate road upgrade works. | WHOBOS Civil | DATETBC | TIME10am - 3pm |
To report a safety or accident hazard please contact the City or report the incident online via the City's
Make a Request page.
Details of other road works in the City can be found on the
construction and maintenance work page of the website.
* Upcoming works/events may not yet be approved. Dates and times may be subject to change.
Media contact
- Phone 9474 0777
- Email media@southperth.wa.gov.au