Manning Road Shared Path – Goss Avenue to Gillon Street
As part of the Canning Bridge to Curtin University Bike Link project, a new shared path for walking and riding will run parallel to Manning Road, from Goss Avenue to Gillon Street, where it will join the existing on-road bike lane on Walanna Drive.
The works will include approximately 880 metres of new asphalt pathway, new kerb installation, drainage, reticulation modifications and minor shrub removal/relocation.
Construction of the path will happen in seven stages and take approximately five months to complete.
Project Schedule
Commencement Date | Stage |
10 January 2024 | Stage 2 |
27 January 2024 | Stage 7 |
Late January 2024 | Stage 1 |
Early March 2024 | Stage 3 |
March 2024 | Stage 4 |
April 2024 | Stage 6 |
May 2024 | Stage 5 |
Project Map
Road Works
The road works will primarily involve rehabilitating the existing road surface. The City will also be installing a speed hump at the entry of Goss Avenue, from Manning Road and a raised intersection plateau at the intersection of Goss Avenue and Pether Road to improve safety within the area. Additional civil works such as replacing sections of kerb and pram ramps and the installation of a new vehicle access path into George Burnett Park will also take place during the construction period.
Resurfacing works are scheduled to take place on two occasions during the works period. Nearby and/or affected residents will receive a further letter 48 hours prior to the laying of new asphalt. Driving on freshly laid asphalt can negatively affect the quality of the asphalt and increase the risk of bitumen sticking to car tyres. Vehicle movements in and out of some properties will be impacted during these resurfacing works.
Working Hours and traffic management
Construction works are scheduled between 7am and 5pm, Monday to Friday, although it may be necessary to carry out some activities outside of these hours, including Saturdays.
Temporary road closures and detours will be implemented to facilitate the works. For the safety of road users and construction personnel, please follow signage and take care when driving in the area. Should you need to enter or exit your property while works are in progress, please speak to the traffic controllers who will direct you through the work site. During construction on-street parking within the works area will also be prohibited.
Frequently Asked Questions
What's involved in the project?
The Manning Shared Path project will include approximately 880 metres of new asphalt pathway as well as new kerb installation, drainage, reticulation modifications and minor shrub removal/relocation.
Will the works be happening on the weekend?
No. Works will occur on weekdays only.
Will I be able to access George Burnett Leisure Centre (GBLC)?
The George Burnett Leisure Centre will remain accessible over the course of the project.
Will the Farmers Market on Manning still be running?
The Farmers Market on Manning has been consulted as part of the works and will continue to operate throughout the project. There may be some temporary changes to the setup of the market and the parking layout on select dates to accommodate the works.
How can I find out more about the Canning Bridge to Curtin University Bike Link project and the stakeholder engagement that has taken place?
Find out more at yoursay.southperth.wa.gov.au/bikelink.
If you have any queries do not hesitate to contact the City on 9474 0777 or raise a request.