Weekly approved works 2-8 October 2023
Approved works in the City of South Perth for 2-8 October 2023.
Civic Heart works
Civic Heart is a major development that will include two buildings of 39 and 22 storeys, and provide 309 residential dwellings, commercial and retail tenancies. The site is located at 1-3 Mends St in South Perth.
Construction commenced in January 2021 and is expected to take three years to complete. Residents with enquiries can email the builder directly at civicheart@hanssen.com.au.
DETAILS OF WORKS | WHO | DATE | TIME |
General construction activities contained on site. Northbound closure and truck access to/from Mends St. Southbound lane closure on Labouchere Rd southbound for general construction operations and deliveries. No right turn permitted
between Labouchere Rd and Bowman St and Labouchere Rd and Lyall St. | Hanssen Construction | Ongoing | 7am-6pm |
Construction site - general works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
1 Richardson St | South Perth | General construction operations contained on site. | EMCO Building | 2 - 7 Oct | 7am-6pm |
1-3 Mends St (Civic Heart) | South Perth | General construction activities contained on site. Northbound closure and truck access to/from Mends St. Southbound lane closure on Labouchere Rd southbound for general construction operations and deliveries. No right turn permitted between Labouchere Rd and Bowman St and Labouchere Rd and Lyall St. | Hanssen Construction | 2 - 7 Oct | 7am-6pm |
15 South Perth Esp | South Perth | General construction operations contained on site, some truck movements via South Perth Esp. | Giorgi | 2 - 7 Oct | 7am - 5pm |
17 Clydesdale St (Abode Apartments) | Como | General construction operations contained on site. | Jabiru Construction | 2 - 7 Oct | 7am - 6pm |
124 Lockhart Street | Como | General construction activities and truck movement on Lockhart St and Edgecumbe St. | Sale Alcock | 2 - 7 Oct | 7am - 5pm |
150 Robert St | Como | General construction activities and truck movements on Robert St. | Thomas Building | 2 - 7 Oct | 7am-5pm |
47 Clydesdale St | Como | General construction activities and truck movements on Clydesdale St. | Danmar Developments | 2 - 7 Oct | 7am-5pm |
69 South Perth Esp | South Perth | General construction activities and truck movements on Harper Tce and South Perth Esp. | Encon | 2 - 7 Oct | 7am-5pm |
8 Parker St | South Perth | General construction activities and truck movements on Parker St. | Built | 2 - 7 Oct | 7am-5pm |
Construction site - additional works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
1 Richardson Street | South Perth | Richardson Street and Melville Parade closed eastbound with detour for concrete pour | EMCO Building | 6 Oct |
Road works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
Mends St and Labouchere Rd | South Perth | Road closures and detours for Mends St between Labouchere Rd and Mill Point Rd. To facilitate road upgrade works. | BOS Civil | 2 Oct -11 Nov | 7am - 6pm |
Manning Road | Manning | Road Resurfacing Nightworks | City of South Perth/WCP Civil | 4 Oct | 9pm - 5am |
Long term works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
6 Hopetoun St | South Perth | General construction activities and truck movements. | GreenbuiltWA | Oct-Dec 23 | 7am-5pm |
24 Mends St | South Perth | Footpath obstruction and pedestrian management | Southern Cross | 2 - 21 Oct | 7am - 5pm |
Godwin Avenue | Manning | Stormwater Sumps Upgrade and Cycle Path Extension | City of South Perth | 2 Oct | 7am - 5pm |
Services works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
80 Mill Point Rd | South Perth | Lateral shift on Mill Point Road at Ferry Street and pedestrian management for telecommunications works | Linkforce / LGC Traffic Management | 2 Oct | 7am - 5pm |
Short-term low-impact works/ events
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
Labouchere Rd (Richardson - Angelo) | South Perth | Southbound lane closure on Labouchere Road (Richardson - Angelo) for site demobilisation. | Crothers Construction | 3 Oct | 7am - 3pm |
Upcoming works / events (works may not yet be approved; dates and times may be subject to change)
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
Labouchere Road | South Perth | Subject to approval Lane closures northbound and southbound on Labouchere Road between Mill Point Road and Mends Street. To facilitate road upgrade works | BOS Civil | 16 Oct - 3 Nov | 7pm - 6am |
Labouchere Road | South Perth | Subject to approval Northbound lane closures on Labouchere Road between Mill Point Road and Mends Street. To facilitate road upgrade works | BOS Civil | 16 Oct - 3 Nov | 10am - 3pm |
To report a safety or accident hazard please contact the City or report the incident online via the City's
Make a Request page.
Details of other road works in the City can be found on the
construction and maintenance work page of the website.
* Upcoming works/events may not yet be approved. Dates and times may be subject to change.
Media contact
- Phone 9474 0777
- Email media@southperth.wa.gov.au