Weekly approved works 10-18 April 2023
Approved works in the City of South Perth for 10-18 April 2023.
Civic Heart works
Civic Heart is a major development that will include two buildings of 39 and 22 storeys, and provide 309 residential dwellings, commercial and retail tenancies. The site is located at 1-3 Mends Street in South Perth.
Construction commenced in January 2021 and is expected to take three years to complete. Residents with enquiries can email the builder directly at civicheart@hanssen.com.au.
DETAILS OF WORKS | WHO | DATE | TIME |
General construction activities contained on site. Northbound closure and truck access to/from Mends Street. Southbound lane closure on Labouchere Road southbound for general construction operations and deliveries. No right turn permitted between Labouchere Road and Bowman Street and Labouchere Road and Lyall Street. | Hanssen Construction | Ongoing | 7am-6pm |
Construction site - general works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
1 Richardson Street | South Perth | Concrete pour General construction operations contained on site. | EMCO Building | 12 Apr 11-15 Apr | 5-7am 7am-6pm |
1-3 Mends Street (Civic Heart) | South Perth | General construction activities contained on site. Northbound closure and truck access to/from Mends St. Southbound lane closure on Labouchere Rd southbound for general construction operations and deliveries. No right turn permitted between Labouchere Rd and Bowman St and Labouchere Rd and Lyall St. | Hanssen Construction | 11-15 Apr | 7am-6pm |
15 South Perth Esplanade | South Perth | General construction operations contained on site, some truck movements via South Perth Esplanade. | Giorgi | 11-15 Apr | 7am-5pm |
17 Clydesdale Street (Abode Apartments) | Como | General construction operations contained on site. | JCM Property Group | 11-15 Apr | 7am-6pm |
6 Hopetoun Street | South Perth | General construction activities and truck movements. | Greenbuilt WA | 11-15 Apr | 7am-5pm |
69 South Perth Esplanade | South Perth | General construction activities and truck movements on Harper Terrace and South Perth Esplanade. | 11-15 Apr | 7am-5pm | |
8 Parker Street | South Perth | General construction activities and truck movements on Parker Street. | Built | 11-15 Apr | 7am-5pm |
2 Edgecumbe Street | Como | General construction activities and truck movements on Edgecumbe Street. | Kastle | 11-15 Apr | 7am-6pm |
47 Clydesdale Street | Como | General construction activities and truck movements on Clydesdale Street. | Danmar Developments | 11-15 Apr | 7am-5pm |
Labouchere Rd (Richardson - Angelo) | South Perth | Ongoing truck access from/to Labouchere Road southbound. | Crothers Construction | 11-15 Apr | Mon-Fri 7am-7pm |
EMCO Building, out of hours concrete pour
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
1-3 Richardson St | South Perth | Concrete pour | EMCO Building | 17 Apr & 15 Jun | 5am-7am (after which time normal construction hours apply) |
Roadworks
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
South Perth Esplanade | South Perth | Traffic control on South Perth Esplanade for road reconstruction activities. | City of South Perth/WCP | 10-18 Apr | 7am - 5 pm |
South Perth Esplanade | South Perth | South Perth Esplanade car park (SPE4) closure for road reconstruction activities. | City of South Perth/WCP | 10-18 Apr | 24/7 |
Long term works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
None notified |
|
Services works
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
Mill Point Rd (Onslow St - Mends St) | South Perth | Westbound lane closures in multiple locations to facilitate street light inspection works. | Utility Asset Management / Western Power | 11-12 Apr | 10am-2pm |
Labouchere Rd (Mends St-Bowman St) | South Perth | Northbound lane closure to facilitate street light inspection works. | Utility Asset Management / Western Power | 11-12 Apr | 10am-2pm |
South Perth Esplanade | South Perth | Closure of Ray St at South Perth Esplanade for crossover reconstruction. | City of South Perth / WCP | 13-14 Apr | 7am-5pm |
South Perth Esplanade | South Perth | Closure of South Perth Esplanade east of Mends St and detour for road reconstruction activities. | City of South Perth / WCP | 13-14 Apr | 7am-5pm |
Banksia Tce (Mill Point Road - Canning Hwy) | South Perth | Sewer relining works, works contained on verge areas. | Water Corporation | Apr-Jun 23 | 7am-5pm |
Labouchere Rd (Comer Street - Eric St) | Como | Sewer relining works southbound Labouchere Rd, works contained on verge areas. | Water Corporation | Apr-Jun 23 | 7am-5pm |
Ryrie Av (Murray Street - Bland Stt) | Como | Sewer relining works, works contained on verge areas. | Water Corporation | Apr-Jun 23 | 7am-5pm |
Downey Dr (Welwyn Av - Marsh Av) | Manning | Sewer relining works, works contained on verge areas. | Water Corporation | Apr-Jun 23 | 7am-5pm |
Banksia Tce (View Street - Third Av) | Kensington | Sewer relining works, westbound on Banskia Terrace works contained on verge areas. | Water Corporation | Apr-Jun 23 | 7am-5pm |
Short term low impact works/ events
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
None notified |
Upcoming works/ events (works may not yet be approved; dates and times may be subject to change)
LOCATION | SUBURB | DETAILS OF WORKS | WHO | DATE | TIME |
South Perth Esplanade | South Perth | Closure of Ray Street at South Perth Esplanade for crossover reconstruction. | City of South Perth/WCP | 17-18 Apr | 2pm (17th) - 6am (18th) |
South Perth Esplanade | South Perth | Closure of South Perth Esplanade east of Mends Street and detour for road reconstruction activities. | City of South Perth/WCP | 17-18 Apr | 2pm (17th) - 6am (18th) |
To report a safety or accident hazard please contact the City or report the incident online via the City's
Make a Request page.
Details of other road works in the City can be found on the
construction and maintenance work page of the website.
* Upcoming works/events may not yet be approved. Dates and times may be subject to change.
Contact us
- Phone 9474 0777