Weekly approved works 20-26 February 2023

Public Notice 20 February 2023
Road Works

Approved works in the City of South Perth for 20-26 February 2023.

Civic Heart works

Civic Heart is a major development that will include two buildings of 39 and 22 storeys, and provide 309 residential dwellings, commercial and retail tenancies. The site is located at 1-3 Mends Street in South Perth. 

Construction commenced in January 2021 and is expected to take three years to complete. Residents with enquiries can email the builder directly at civicheart@hanssen.com.au.

DETAILS OF WORKSWHODATETIME
General construction activities contained on site. Northbound closure and truck access to/from Mends Street. Southbound lane closure on Labouchere Road southbound for general construction operations and deliveries.
No right turn permitted between Labouchere Road and Bowman Street and Labouchere Road and Lyall Street.
Hanssen Construction
Ongoing7am-6pm

Construction site - general works

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
1 Richardson StreetSouth PerthGeneral construction operations contained on site.EMCO Building20-25 Feb7am-6pm
1-3 Mends Street (Civic Heart)South Perth

General construction activities contained on site. Northbound closure and truck access to/from Mends St. Southbound lane closure on Labouchere Rd southbound for general construction operations and deliveries.

No right turn permitted between Labouchere Rd and Bowman St and Labouchere Rd and Lyall St.

Hanssen Construction20-25 Feb7am-6pm
11 Melville Parade (Southscape)South PerthGeneral construction operations contained on site.Thomas Building20-25 FebM-F 7am-5.30pm
Sat 7am-3pm
15 South Perth EsplanadeSouth Perth
General construction operations contained on site, some truck movements via South Perth Esp.
Giorgio20-25 Feb7am-5pm
17 Clydesdale Street (Abode Apartments)ComoGeneral construction operations contained on site.JCM Property Group

20-25 Feb

7am-6pm
6 Hopetoun StreetSouth PerthGeneral construction activities and truck movements.Greenbuilt WA20-25 Feb7am-5pm
69 South Perth EsplanadeSouth PerthGeneral construction activities and truck movements on Harper Tce and South Perth Esp.Encon20-25 Feb
7am-5pm
8 Parker StreetSouth Perth

General construction activities and truck movements on Parker St.

Built20-25 Feb
7am-5pm
2 Edgecumbe StreetComoGeneral construction activities and truck movements on Edgecumbe St.Kastle20-25 Feb
7am-6pm
47 Clydesdale StreetComoGeneral construction activities and truck movements on Clydesdale St.Danmar Developments20-25 Feb
7am-5pm
Labouchere Rd (Richardson - Angelo)South PerthOngoing truck access from/to Labouchere Road southboundCrothers Construction20-25 FebM-F
7am-7pm

Construction site - additional works 

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
1 Richardson Street

South Perth

Richardson Street and Melville Parade closed eastbound with detour for concrete pourEMCO Building21 & 23 February5am - 5pm

Roadworks

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
Hobbs Avenue, Murray St to Blamey PlComoRoad rehabilitation works - Hobbs Ave will be closed to through traffic between Murray St and Blamey Pl with detours in placeCity of South Perth20-24 Feb7am-5pm

Long term works

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
South Perth EsplanadeSouth PerthOperation of Autonomous bus trials on South Perth Esp, Mill Point Cl and Mill Point Rd. Operations will be Tuesday to Sunday weekly.RAC21-26 Feb 

Tues-Fri 9am-5pm

Sat-Sun 11am-5pm

Services works

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
Angelo StreetSouth PerthVerge works at Angelo St / Onslow St and pedestrian management for Western Power line worksCable Layers Australia / Western Power20 - 24 Feb7am - 5pm
Angelo Street (Onslow St - Labouchere Rd)South PerthVerge works and footpath closure westbound with pedestrian management for Western Power line worksCable Layers Australia / Western Power20 - 24 Feb7am - 5pm
Labouchere Rd (Angelo St - Richardson St)South PerthVerge works and footpath closure with pedestrian management northbound Labouchere Road for Western Power line worksCable Layers Australia / Western Power20 - 24 Feb7am - 5pm
Labouchere Rd (Richardson St - Mill Point Rd)South Perth

Northbound lane closures on Labouchere Road from Richardson St - Bowman St for Western Power line works

Cable Layers Australia / Western Power20 - 24 Feb9am - 3pm
Mill Point Rd (North)South PerthVerge works and lateral shift northbound on Mill Point Rd north of Labouchere Rd for Western Power line works.Cable Layers Australia / Western Power20 - 24 Feb7am - 5pm
Banksia Terrace (Mill Point Road - Canning Highway)South PerthSewer relining works, works contained on verge areas.Water CorporationFeb-Jun 23 7am - 5pm
Labouchere Road (Comer Street - Eric Street)ComoSewer relining works southbound Labouchere Rd, works contained on verge areas.Water CorporationFeb-Jun 23 7am - 5pm
Ryrie Avenue (Murray Street - Bland Street)ComoSewer relining works, works contained on verge areas.Water CorporationFeb-Jun 23 7am - 5pm
Downey Drive (Welwyn Avenue - Marsh Avenue)ManningSewer relining works, works contained on verge areas.Water CorporationFeb-Jun 23 7am - 5pm
Banksia Terrace (View Street - Third Avenue)KensingtonSewer relining works, westbound on Banskia Tce works contained on verge areas.Water CorporationFeb-Jun 23 
7am - 5pm

Short term low impact works/ events

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
None notified 
  

Upcoming works/ events (works may not yet be approved; dates and times may be subject to change)

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
Mill Point RoadSouth PerthNightworks - eastbound lane closure between Harper Terrace and Darley Street for drainage repair works.City of South Perth28 February12am-5am

To report a safety or accident hazard please contact the City or report the incident online via the City's Make a Request page. Details of other road works in the City can be found on the construction and maintenance work page of the website.

* Upcoming works/events may not yet be approved. Dates and times may be subject to change.

Contact us

For more information, please contact the City.