Approved works in the City of South Perth for 19-25 December 2022. 

Civic Heart works

Civic Heart is a major development that will include two buildings of 39 and 22 storeys, and provide 309 residential dwellings, commercial and retail tenancies. The site is located at 1-3 Mends Street in South Perth. 

Construction commenced in January 2021 and is expected to take three years to complete. Residents with enquiries can email the builder directly at civicheart@hanssen.com.au.

DETAILS OF WORKSWHODATETIME
General construction activities contained on site. Northbound closure and truck access to/from Mends Street. Southbound lane closure on Labouchere Road southbound for general construction operations and deliveries.
No right turn permitted between Labouchere Road and Bowman Street and Labouchere Road and Lyall Street.
Hanssen Construction
Ongoing7am-6pm

Construction site - general works

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
1 Richardson StreetSouth PerthGeneral construction operations contained on site.EMCO Building19-23 Dec7am-6pm
1-3 Mends Street (Civic Heart)South Perth

General construction activities contained on site. Northbound closure and truck access to/from Mends Street. Southbound lane closure on Labouchere Road southbound for general construction operations and deliveries.

No right turn permitted between Labouchere Road and Bowman Street and Labouchere Road and Lyall Street.

Hanssen Construction19-23 Dec7am-6pm
11 Melville Parade (Southscape)South PerthGeneral construction operations contained on site.Thomas Building19-23 DecM-F 7am-5.30pm
Sat 7am-3pm
15 South Perth EsplanadeSouth Perth
General construction operations contained on site, some truck movements via South Perth Esplanade.
Giorgio19-24 Dec7am-5pm
17 Clydesdale Street (Abode Apartments)ComoGeneral construction operations contained on site.JCM Property Group

19-23 Dec

7am-6pm
6 Hopetoun StreetSouth PerthGeneral construction activities and truck movements.Greenbuilt WA13-1819-23 Dec7am-5pm
69 South Perth EsplanadeSouth PerthGeneral construction activities and truck movements on Harper Terrace and South Perth Esplanade.Encon19-23 Dec
7am-5pm
8 Parker StreetSouth Perth

General construction activities and truck movements on Parker Street.

Built19-23 Dec
7am-5pm
2 Edgecumbe StreetComoGeneral construction activities and truck movements on Edgecumbe Street.Kastle19-23 Dec
7am-6pm
47 Clydesdale StreetComoGeneral construction activities and truck movements on Clydesdale Street.Danmar Developments19-23 Dec
7am-5pm
Labouchere Road (Richardson Street - Angelo Street) South PerthOngoing truck access from/to Labouchere Road southbound. Crothers Construction19-23 Dec
M-F 7am-5pm

Construction site - additional works 

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
None notified  
 

Roadworks

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
None notified

Long term works

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
None notified  

 

Services works

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
Banksia Tce (Mill Point Rd - Canning Hwy)South PerthSewer relining works, works contained on verge areas.Water CorporationDec 22 - Jun 237am - 5pm
Labouchere Rd (Comer St - Eric St)ComoSewer relining works southbound Labouchere Rd, works contained on verge areas.Water CorporationDec 22 - Jun 237am - 5pm
Ryrie Ave (Murray St - Bland St)ComoSewer relining works, works contained on verge areas.Water CorporationDec 22 - Jun 237am - 5pm
Downey Dr (Welwyn Ave - Marsh Ave)ManningSewer relining works, works contained on verge areas.Water CorporationDec 22 - Jun 237am - 5pm
Banksia Tce (View St - Third Ave)KensingtonSewer relining works, westbound on Banskia Tce works contained on verge areas.Water CorporationDec 22 - Jun 237am - 5pm

Short term low impact works/ events

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
Mends StreetSouth PerthRoad closure between Mill Point Road and South Perth Esplanade for crane lifting operations.LGC / General Crane Services
20-21 Dec8pm-6am

Upcoming works/ events (works may not yet be approved; dates and times may be subject to change)

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
Angelo Street South Perth 
Subject to approval
Verge works at Angelo St / Onslow St and pedestrian management for Western Power line works.

Cable Layers Australia / Western PowerTBCTBC
Angelo Street (Onslow St - Labouchere Rd)South Perth 
Subject to approval
Verge works and footpath closure westbound with pedestrian management for Western Power line works.
Cable Layers Australia / Western PowerTBCTBC
Labouchere Rd (Angelo St - Richardson St)South Perth 
Subject to approval
Verge works and footpath closure with pedestrian management northbound Labouchere Road for Western Power line works.

Cable Layers Australia / Western PowerTBCTBC
Labouchere Rd (Richardson St - Mill Point Rd)South Perth
Subject to approval
Northbound lane closures on Labouchere Road from Richardson St - Bowman St for Western Power line works.
Cable Layers Australia / Western PowerTBCTBC
Mill Point Rd (North) South Perth 
Subject to approval
Verge works and lateral shift northbound on Mill Point Rd north of Labouchere Rd for Western Power line works.
Cable Layers Australia / Western PowerTBCTBC
Labouchere Rd (Mends St - Mill Point Rd)South Perth 
Subject to approval
Southbound and northbound lane closures on Labouchere Road from Hardy St - Mill Point Road for Western Power connection works.
Cable Layers Australia / Western PowerTBC7am-6pm

To report a safety or accident hazard please contact the City or report the incident online via the City's Make a Request page. Details of other road works in the City can be found on the construction and maintenance work page of the website.

* Upcoming works/events may not yet be approved. Dates and times may be subject to change.

Contact us

For more information, please contact the City.