Weekly approved works 21-28 March 2022

News Update 22 March 2022
Road Works

Approved works in the City of South Perth for 21-28 March 2022.

Civic Heart works

Civic Heart is a major development that will include two buildings of 39 and 22 storeys, and provide 309 residential dwellings, commercial and retail tenancies. The site is located at 1-3 Mends Street in South Perth. 

Construction commenced in January 2021 and is expected to take three years to complete. Residents with enquiries can email the builder directly at civicheart@hanssen.com.au.

DETAILS OF WORKSWHODATETIME
General construction activities contained on site. Northbound closure and truck access to/from Mends Street. Southbound lane closure on Labouchere Road southbound for general construction operations and deliveries.
No right turn permitted between Labouchere Road and Bowman Street and Labouchere Road and Lyall Street.
Hanssen Construction
Ongoing7am-6pm

Construction site - general works


LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
11 Melville Parade (Southscape)South PerthGeneral construction operations contained on site.Thomas Building21-26 MarM-F 7am-5.30pm
Sat 7am-3pm
19 Clydesdale Street (Parkview)ComoGeneral construction operations contained on site.JCM Property Group21-26 Mar7am-6pm
4 Paterson StreetManningHalf road closure of Paterson Street for general construction operations.Customised Projects21-26 Mar
7am-5pm
47 Clydesdale Street
Como
General construction activities and truck movements on Clydesdale Street.
Danmar Developments21-26 Mar
7am-5pm
51 Angelo StreetSouth PerthGeneral construction activities and truck movements on Angelo Street.Focus Building21-26 Mar
7am-5pm
6 Hopetoun StreetSouth PerthGeneral construction activities and truck movements.Greenbuilt WA21-26 Mar
7am-5pm
69 South Perth EsplanadeSouth PerthGeneral construction activities and truck movements on Harper Terrace and South Perth Esplanade.Encon21-26 Mar
7am-5pm
8 Parker StreetSouth Perth

General construction activities and truck movements on Parker Street.

Built21-26 Mar
7am-5pm
9 Bradshaw CrescentManningFootpath diversion in place 24/7 for general construction activities and truck movements.EMCO Building21-26 Mar
7am-5pm

Construction site - additional works

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
17 Clydesdale Street (Abode ApartmentsComoLane closure and traffic control on Clydesdale St and McDougall St for concrete pourJCM Property Group23 March7am-6pm
69 South Perth EsplanadeSouth PerthSubject to final approval
Full road closure on north end of Harper Terrace between South Perth Esplanade and Mill Point Road for concrete pour.
Encon25 March7am-5pm
51 Angelo StreetSouth Perth

Final exposed suspended deck concrete pour

Focus Building Company

23 March4.30am-7pm

Roadworks

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
None notified

Long term works

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
None notified
     

Services works

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
None notified

Short term low impact works/events

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
None notified     

Upcoming works*

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
9 Mends St (Mill Point Rd)South Perth
Lane closure eastbound for Western Power connection works.
LGC Traffic Management4-5 Apr7pm-7am
51 Angelo StreetSouth PerthSubject to approval
Road closure westbound Angelo Street for concrete pour.
Focus BuildingTBCTBC
17 Clydesdale Street (Abode Apartments)ComoSubject to final approval
General construction operations contained on site.
JCM Property GroupTBC7am-6pm
1 Richardson StreetComoSubject to final approval
General construction operations contained on site.
EMCO BuildingTBC7am-6pm
To report a safety or accident hazard please contact the City or report the incident online via the City's Make a Request page. Details of other road works in the City can be found on the construction and maintenance work page of the website.

* Upcoming works/events may not yet be approved. Dates and times may be subject to change.

Contact us

For more information, please contact the City.