Weekly approved works 13-19 December 2021

News Update 14 December 2021
Road Works

Approved works within the City of South Perth for 13-19 December 2021.

Civic Heart works

Civic Heart is a major development that will include two buildings of 39 and 22 storeys, and provide 309 residential dwellings, commercial and retail tenancies. The site is located at 1-3 Mends Street in South Perth. 

Construction commenced in January 2021 and is expected to take three years to complete. Residents with enquiries can email the builder directly at civicheart@hanssen.com.au.

DETAILS OF WORKSWHODATETIME
General construction activities contained on site. Northbound closure and truck access to/from Mends Street. Southbound lane closure on Labouchere Road southbound for general construction operations and deliveries.
No right turn permitted between Labouchere Road and Bowman Street and Labouchere Road and Lyall Street.
Hanssen Construction
Ongoing7am-6pm

Construction site - general works


LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
19 Clydesdale Street (Parkview)ComoGeneral construction operations contained on site.JCM Property Group13-18 Dec7am-6pm
11 Melville Parade (Southscape)ComoGeneral construction operations contained on site.Thomas Building13-18 DecM-F 7am-5.30pm
Sat 7am-3pm
24 Wooltana StreetComoGeneral construction activities contained on site.Daly & Shaw Building/Kwik Logistics13-18 Dec
7am-6pm
4 Paterson StreetManningHalf road closure of Paterson Street for general construction operations.Customised Projects13-18 Dec
7am-5pm
47 Clydesdale Street
Como
General construction activities and truck movements on Clydesdale Street.
Danmar13-18 Dec
7am-5pm
51 Angelo StreetSouth PerthGeneral construction activities and truck movements on Angelo Street.Focus Building13-18 Dec
7am-5pm
6 Hopetoun StreetSouth PerthGeneral construction activities and truck movements.GreenbuiltWA13-18 Dec
7am-5pm
69 South Perth EsplanadeSouth PerthGeneral construction activities and truck movements on Harper Terrace and South Perth Esplanade.Encon13-18 Dec
7am-5pm
8 Henley Street (Paradiso)ComoGeneral construction operations.Pyramid Constructions13-18 Dec
7am-5pm
8 Parker StreetSouth Perth

General construction activities and truck movements on Parker Street.

Built13-18 Dec
7am-5pm
9 Bradshaw CrescentManningFootpath diversion in place 24/7 for general construction activities and truck movements.EMCO Building13-18 Dec
7am-5pm

Construction site - additional works

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
8 Parker StreetSouth Perth

Concrete pour 

Built17 Dec6am-9pm

Roadworks

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
Kwinana Freeway - Mill Point Road on rampSouth PerthRoad closed for the installation and removal of traffic data loggersMain Roads WA13 Dec 9pm-1am

Long term works

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
South Perth EsplanadeSouth PerthOperation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road. General operations will be Tuesday to Sunday weekly.RAC14-19 Dec

Tue-Wed 9am-1pm

Thur-Fri 9am-5pm

W/E 12pm-5pm

South Perth EsplanadeSouth PerthUpgrade of northern section of PSP along foreshore. Diversions in place for cyclists onto road carriageway.City of South Perth13-18 Dec7am-5pm

Services works

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
Como (Collier Project)ComoVerge and road lane works with lane closures, traffic control and pedestrian management for Western Power Collier Underground Power Project.
Genus/ Western Power13-18 Dec7am-5.30pm
9am-3pm (SZ)
Lockhart Street Water Main ReplacementComoVerge and road lane works with lane closures, traffic control and pedestrian management for WaterCorp Watermain replacement projectCivcon Pty Ltd13-18 Dec24hrs

 

Short term low impact works/events

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
None notified     

 

Upcoming works*

LOCATIONSUBURBDETAILS OF WORKSWHODATETIME
2 Edgecumbe StreetComo
Subject to updated approval
General construction activities and truck movements on Edgecumbe Street.
TBCTBCTBC
Kwinana Freeway - Mill Point Road on rampSouth PerthRoad closed for the installation and removal of traffic data loggersMain Roads WA21 Dec8pm-1am
To report a safety or accident hazard please contact the City or report the incident online via the City's Make a Request page. Details of other road works in the City can be found on the construction and maintenance work page of the website.

* Upcoming works/events may not yet be approved. Dates and times may be subject to change.