Weekly approved works 26 April - 2 May 2021

News Update 27 April 2021
Road Works

Approved works within the City of South Perth for 26 April - 2 May 2021.

Construction site - general works

LOCATION SUBURB DETAILS OF WORKS WHO DATE TIME

1-3 Mends Street (Civic Heart)

South Perth General construction activities contained on site. Northbound closure and Truck access to/from Mends Street. No right turn from Labouchere Road into Bowman Street. Hanssen Construction
27 Apr-1 May 7am-6pm
19 Clydesdale Street (Parkview)  Como  General construction operations contained on site. JCM Property Group  27 Apr-1 May 7am-6pm 
2 Edgecumbe Street Como  General construction activities and truck movements on Edgecumbe Street.  Jaxon Construction 27 Apr-1 May 7am-7pm
24 Wooltana Street  Como  General construction activities contained on site.   Daly & Shaw  Building / Kwik Logistics  27 Apr-1 May
7am-6pm 
4 Paterson Street  Manning  Half road closure of Paterson Street for general construction operations.  Customised Projects  27 Apr-1 May 7am-5pm 
47 Clydesdale Street
Como
General construction activities and truck movements on Clydesdale Street.
Danmar Developments
27 Apr-1 May
7am-5pm
69 South Perth Esplanade South Perth General construction activities and truck movements on Harper Terrace and South Perth Esplanade. Encon 27 Apr-1 May 7am-5pm
8 Henley Street (Paradiso)  Como  General construction operations, including crane operations under traffic control.  Pyramid Constructions  27 Apr-1 May 7am-5pm 

Construction site - additional works

LOCATION SUBURB DETAILS OF WORKS WHO DATE TIME
69 South Perth Esplanade  South Perth Road closure on north end of Harper Terrace between South Perth Esplanade and Mill Point Road for concrete panel installation. Econ  28 Apr  7am-7pm 

Roadworks

LOCATION SUBURB DETAILS OF WORKS WHO DATE TIME
South Terrace  South Perth  Road rehabilitation works  WCP / CoSP  27 April - 25 May  27 Apr-25 May
Dyson St & View St  Kensington  Road rehabilitation works  Asphaltech / CoSP  27 Apr - 20 May  27 Apr-20 May 

Long term works

LOCATION SUBURB DETAILS OF WORKS WHO DATE TIME
South Perth Esplanade  South Perth Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road. General operations will be Thursday to Saturday weekly. RAC 29 Apr - 1 May 9am-3pm

Services works

LOCATION SUBURB DETAILS OF WORKS WHO DATE TIME
Como (Collier Project) Como Verge and road lane works with lane closures, traffic control and pedestrian management for Western Power Collier Underground Power Project.
Diamond Underground Services / Western Power 27 Apr-1 May
7am-5pm
9am-3pm (SZ)

Short term low impact works/events

LOCATION SUBURB DETAILS OF WORKS WHO DATE TIME
1 Hardy Street
South Perth
Subject to final approval
Half road closure and traffic control stop/slow for crane operations.
Kwik Logistics / Buss Roof Plumbing
30 April
7am-12pm 

Upcoming works*

LOCATION SUBURB DETAILS OF WORKS WHO DATE TIME
1 Hardy Street  South Perth  Subject to final approval
Half road closure and traffic control stop/slow for crane operations. 
Kwik Logistics / Buss Roof Plumbing  17 May  7am-12pm 
8 Parker Street South Perth Subject to approval
General construction activities and truck movements on Parker Street.
 Built TBC TBC 

 

To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.

Details of other road works in the City can be found on the construction and maintenance work page of the website.

* Upcoming works/events may not yet be approved. Dates and times may be subject to change.