South Perth Station Precinct works: 15-21 April 2019
Approved works within the South Perth Station Precinct for 15-21 April 2019:
LOCATION | DETAILS OF WORKS | WHO | DATE | TIME |
Construction site - abnormal works* | ||||
69 South Perth Esplanade | Demolition operations - truck movements on Harper Terrace, all works to be contained within the site. | Brajkovich Demolition |
15-30 April | 7am-7pm |
South Perth Esplanade / Mends Street | Single lane flow on South Perth Esplanade to facilitate concrete pour operations. |
Connect South / MG Group |
15-16 April | 7am-12pm |
South Perth Esplanade / Mends Street |
Road closure on South Perth Esplanade and Mends Street with traffic control on Ray Street for local resident access. | Connect South / MG Group |
16-17 April | 7pm-6am |
South Perth Esplanade / Mends Street |
Single lane flow on South Perth Esplanade to facilitate construction operations. | Connect South / MG Group |
17 April | 6am-4pm |
Construction site - general approvals** | ||||
39 Mends Street (Echelon) |
Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours. |
Giorgi |
15-20 April |
7am-5pm |
26 Charles Street | General truck movements on Charles Street, footpath closure and detour for construction operations. Traffic management for truck access to 12 Charles Street. | Cockram Constructions |
15-20 April | 7am-5pm |
Services works | ||||
Mends Street | Road closure for trenching associated with Water Corporation service connection works. | Water Corporation | 17 April | 7pm-6am |
Mends Street | Verge works - cable pull and underground boring at Stirling Street for the installation of communications cables. |
Optus / Mikcomm | 15-30 April | 7am-5pm |
Long term works | ||||
South Perth Esplanade/Mends Street | Traffic control on South Perth Esplanade for truck access. Footpath detours in place for shared path and jetty access. Partial road closure and temporary realignment of traffic lanes to facilitate road and footpath upgrades. | Connect South / MG Group | Until 2 Jun | 24/7 |
Melville Parade (Richardson St - Hardy St) | Principal shared path detour resulting increased cyclists and pedestrians on Melville Parade. | Main Roads WA | Until 30 June | 24/7 |
South Perth Esplanade | Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road. | RAC | 16-21 April | 9am-5pm |
Upcoming works / events | ||||
26 Charles Street | Lane closure westbound, traffic flow maintained eastbound with traffic control for concrete pour operations. |
Cockram Constructions | 23 April | 7am-7pm |
Mill Point Road / Labouchere Road | Subject to final approval Banner installation works, mobile lane closures on Labouchere Road and Mill Point Road. |
City of South Perth | 29 April | 10am-2pm |
26 Charles Street |
Lane closure westbound, traffic flow maintained eastbound with traffic control for concrete pour operations. |
Cockram Constructions |
30 April | 7am-7pm |
To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.
Details of other road works in the City can be found on the construction and maintenance work page of the website.
*Abnormal works
Abnormal works are one off activities that require significant truck movements, obstructions to movement such as road closures and detours or works outside of the normal working hours. These works are subject to a separate approval process and are considered on an individual basis. Approvals may include the need to notify residents of the temporary change and in the case of works outside of normal working hours require subsequent approvals from the City’s Environmental Health Team and CEO.
**General Approvals
General approvals are granted to construction sites and long-term activities in the Station Precinct for daily activities such as general truck movements for deliveries and minor concrete pours. These works are only to be undertaken during normal working hours (7am – 7pm Monday -Saturday) and do not include works that will have a significant impact on access through/past the site area. General works are subject to a monthly approval process.