South Perth Station Precinct works: 18-24 February 2019
Approved works within the South Perth Station Precinct for 18-24 February 2019:
LOCATION | DETAILS OF WORKS | WHO | DATE | TIME |
Construction site - abnormal works* | ||||
21 Mends Street (Harper Terrace) | Lane closure and traffic control on Harper Terrace for building façade works. | Quest Apartments / Pindan | 18 Feb | 7am-5pm |
South Perth Esplanade | Lane closures on South Perth Esplanade with traffic control on South Perth Esplanade. | Connect South / MG Group |
18 Feb | 9am-4pm |
Construction site - general approvals** | ||||
39 Mends Street (Echelon) |
Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours. |
Giorgi |
18-23 Feb |
7am-5pm |
21 Mends Street (Harper Terrace) |
General construction operations contained on site. |
Quest Apartments/Pindan |
18-23 Feb |
7am-5pm |
26 Charles Street | General truck movements on Charles Street, footpath closure and detour for construction operations. | Cockram Constructions |
18-23 Feb | 7am-5pm |
Long term works | ||||
South Perth Esplanade | Traffic control on South Perth Esplanade for truck access. Footpath detours on place for shared path and jetty access. | Connect South/MG Group | 18-23 Feb | 7am-4pm |
South Perth Esplanade | Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road. | RAC | 19-24 Feb | 9am-5pm |
Melville Parade (Richardson St - Hardy St) |
Principle Shared Path detour resulting increased cyclists and pedestrians on Melville Parade. |
MRWA | 18 Feb-20 Mar | 24/7 |
Short term low impact works/ events | ||||
Mill Point Road & Labouchere Road |
Lane closures on Mill Point Road westbound and Labouchere Road northbound for verge maintenance works. |
City of South Perth | 21 Feb | 9am-2pm |
Upcoming works | ||||
South Perth Esplanade |
Testing of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road. | RAC | 26 Feb | 9am-5pm |
Melville Parade at Charles Street | Gas main installation works on west side of Melville Parade. Works contained within the verge without impact on road or path network. | Civcon WA | TBA | 7am-5pm |
To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.
Details of other road works in the City can be found on the construction and maintenance work page of the website.
*Abnormal works
Abnormal works are one off activities that require significant truck movements, obstructions to movement such as road closures and detours or works outside of the normal working hours. These works are subject to a separate approval process and are considered on an individual basis. Approvals may include the need to notify residents of the temporary change and in the case of works outside of normal working hours require subsequent approvals from the City’s Environmental Health Team and CEO.
**General Approvals
General approvals are granted to construction sites and long-term activities in the Station Precinct for daily activities such as general truck movements for deliveries and minor concrete pours. These works are only to be undertaken during normal working hours (7am – 7pm Monday -Saturday) and do not include works that will have a significant impact on access through/past the site area. General works are subject to a monthly approval process.