South Perth Station Precinct works update: week commencing 17 September

Public Notice 17 September 2018
Maintenance Works Road Works SPSP Traffic

Approved works within the South Perth Station Precinct for the week commencing 17 September 2018:

LOCATION DETAILS OF WORKS WHO DATE TIME
Construction site - abnormal works*
88-90 Mill Point Road Demolition of existing buildings
All works to be confined to site with only impact on Mill Point Road being trucks entering/exiting.
FOCUS Demolition 17-21 Sep 7am-5pm
31 Labouchere Road / Lyall Street
Demolition of existing buildings.
BRAJKOVICH Demolition 17-21 Sep
7am-5pm
5 Harper Terrace (Reva) Large concrete pour Hanssen 17-21 Sep 7am-12pm
Construction site - general approvals**

39 Mends Street (Echelon)

Dewatering, shotcreting piled walls, excavation, formwork and concrete pours. Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours.

Giorgi

17-21 Sep

7am-5pm

21 Mends Street (Harper Terrace)

Concrete pouring to slabs/walls, including concrete trucks entering / exiting the site,
Mobilisation of minor materials and equipment to site for Plumbing, Electrical & Mechanical Works,
Delivery and Installation of Formwork and Scaffold to Site, including delivery trucks entering / exiting the site.

Delivery and Installation Structural Steel and Roof Sheeting,

Quest Apartments/Pindan

17-21 Sep

7am-5pm

5 Harper Terrace (Reva)

General truck movements on Harper Terrace, remedial work on sinkhole, road and diaphragm wall, minor concrete pours.

Hanssen

17-21 Sep

7am-5pm

Other works

South Perth Esplanade

Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road.

RAC

17-22 Sep

8.30am-5.30pm

Upcoming works

Mends Street

Closure of Mends Street (Mill Point Road – South Perth Esplanade) to facilitate crane operations

General Cranes : 0477 776 112 Workforce Road Services : 0437 140 462

Late Sep

9pm-6am             

To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.

Details of other road works in the City can be found on the construction and maintenance work page of the website.

*Abnormal works
Abnormal works are one off activities that require significant truck movements, obstructions to movement such as road closures and detours or works outside of the normal working hours. These works are subject to a separate approval process and are considered on an individual basis. Approvals may include the need to notify residents of the temporary change and in the case of works outside of normal working hours require subsequent approvals from the City’s Environmental Health Team and CEO.
 
**General Approvals
General approvals are granted to construction sites and long-term activities in the Station Precinct for daily activities such as general truck movements for deliveries and minor concrete pours. These works are only to be undertaken during normal working hours (7am – 7pm Monday -Saturday) and do not include works that will have a significant impact on access through/past the site area. General works are subject to a monthly approval process. 

Contact us

For more information, please contact the City or Make a Request online.
  • Phone 9474 0777