South Perth Station Precinct works update: week commencing 10 September
Approved works within the South Perth Station Precinct for the week commencing 10 September 2018:
LOCATION | DETAILS OF WORKS | WHO | DATE | TIME |
Construction site - abnormal works* | ||||
88-90 Mill Point Road | Demolition of existing buildings All works to be confined to site with only impact on Mill Point Road being trucks entering/exiting. |
FOCUS Demolition | 10-15 Sep | 7am-5pm |
31 Labouchere Road / Lyall Street |
Demolition of existing buildings. |
BRAJKOVICH Demolition | 10-15 Sep |
7am-5pm |
5 Harper Terrace (Reva) | Large concrete pour | Hanssen | 11 Sep | 7am-12pm |
Mends Street | Closure of Mends Street (Mill Point Road – South Perth Esplanade) to facilitate crane operations. | General Cranes: 0477 776 112 Workforce Road Services: 0437 140 462 | 10-11 Sep | 9pm-6am |
21 Mends Street (Harper Terrace) | Crane Demobilisation | Pindan | 15 Sep | 6am – 5pm |
Mill Point Road/Harper Terrace | Banner Installations | ATM Traffic Management | 15 Sep | 7am-12pm |
Construction site - general approvals** | ||||
39 Mends Street (Echelon) |
Dewatering, shotcreting piled walls, excavation, formwork and concrete pours. Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours. |
Giorgi |
10-15 Sep |
7am-5pm |
21 Mends Street (Harper Terrace) |
Concrete pouring to slabs/walls, including concrete trucks entering / exiting the site, |
Quest Apartments/Pindan |
10-15 Sep |
7am-5pm |
5 Harper Terrace (Reva) |
General truck movements on Harper Terrace, remedial work on sinkhole, road and diaphragm wall, minor concrete pours. |
Hanssen |
10-15 Sep |
7am-5pm |
Other works |
||||
South Perth Esplanade |
Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road. |
RAC |
11-13 Sep |
8.30am-5.30pm |
Upcoming works |
||||
21 Mends Street (Harper Terrace) |
Tower crane demobilisation with road closure of Harper Terrace. |
Quest Apartments/Pindan |
15 Sep |
TBC |
To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.
Details of other road works in the City can be found on the construction and maintenance work page of the website.
*Abnormal works
Abnormal works are one off activities that require significant truck movements, obstructions to movement such as road closures and detours or works outside of the normal working hours. These works are subject to a separate approval process and are considered on an individual basis. Approvals may include the need to notify residents of the temporary change and in the case of works outside of normal working hours require subsequent approvals from the City’s Environmental Health Team and CEO.
**General Approvals
General approvals are granted to construction sites and long-term activities in the Station Precinct for daily activities such as general truck movements for deliveries and minor concrete pours. These works are only to be undertaken during normal working hours (7am – 7pm Monday -Saturday) and do not include works that will have a significant impact on access through/past the site area. General works are subject to a monthly approval process.
Contact us
- Phone 9474 0777