South Perth Station Precinct works update: week commencing 9 July 2018

Public Notice 9 July 2018
Maintenance Works Road Works SPSP Traffic

Approved works within the South Perth Station Precinct for the week commencing 9 July 2018:

LOCATION DETAILS OF WORKS WHO DATE TIME
Construction site - abnormal works*
21 Mends Street (Harper Terrace)
Demolition works - Mends Street side. Cutting and removal of precast concrete panels with minor truck movements onto Mends Street under traffic control.
Quest Apartments / Pindan
9- 20 July 7am-5pm
39 Mends Street (Echelon) Early morning start concrete pour, truck access via South Perth Esplanade with lane closure and traffic control. Giorgi  9 July  7am-5pm 
5 Harper Terrace (Reva)
Harper Terrace half road closure with reversible flow managed by traffic control for internal concrete pour.
Hanssen 10-11 July 7am-12pm
Construction site - general approvals**
39 Mends Street (Echelon)
Dewatering, shotcreting piled walls, excavation, formwork and concrete pours. Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours. Giorgi
9-14 July 7am-5pm
21 Mends Street (Harper Terrace) Reinforcement steel deliveries and steel fixing, including delivery truck entering/exiting the site, concrete pouring to slabs/columns/walls, including concrete trucks entering/ exiting the site. Mobilisation of minor materials and equipment to site for plumbing, electrical and mechanical works. Delivery and installation of formwork and scaffold to site, including delivery trucks entering/exiting the site. Delivery and installation of precast concrete walls. Delivery and installation of AFS.
Quest Apartments/Pindan 9-14 July 7am-5pm
35 Mends Street Mobilisation of minor materials and equipment to site for plumbing, electrical & formworker, delivery and installation of formwork to site, including delivery trucks entering/exiting the site delivery and installation of block work. Pindan 9-14 July 7am-5pm
1 Stone Street Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street.
Danmar Developments

9-14 July

7am-5pm
5 Harper Terrace (Reva) General truck movements on Harper Terrace, remedial work on sinkhole, road and diaphragm wall, minor concrete pours. Hanssen 9-14 July 7am-5pm
26 Charles Street Bulk earthworks and reduced levels. Some head works for contiguous piles. Preparation for some concrete formwork and reinforcement.
Pindan 9-14 July 7am-5pm
Other works
South Perth Esplanade Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road. RAC 10-15 July 9am-5pm
  Upcoming works
     
South Perth Esplanade  Subject to approvals. Operation of Autonomous bus on South Perth Esplanade, Mill Point Close and Mill Point Road.  RAC  24 July   9am-5pm 
21 Mends Street (Harper Terrace)  Subject to approvals. Tower crane demobilisation with road closure of Harper Terrace.  Quest Apartments/Pindan  28 July  7am-5pm 
South Perth Esplanade  Subject to approvals. Operation of Autonomous bus on South Perth Esplanade, Mill Point Close and Mill Point Road.  RAC  31 August   9am-1pm 

To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.

Details of other road works in the City can be found on the construction and maintenance work page of the website.

*Abnormal works
Abnormal works are one off activities that require significant truck movements, obstructions to movement such as road closures and detours or works outside of the normal working hours. These works are subject to a separate approval process and are considered on an individual basis. Approvals may include the need to notify residents of the temporary change and in the case of works outside of normal working hours require subsequent approvals from the City’s Environmental Health Team and CEO.
 
**General Approvals
General approvals are granted to construction sites and long-term activities in the Station Precinct for daily activities such as general truck movements for deliveries and minor concrete pours. These works are only to be undertaken during normal working hours (7am – 7pm Monday -Saturday) and do not include works that will have a significant impact on access through/past the site area. General works are subject to a monthly approval process.

Contact us

For more information, please contact the City or Make a Request online.
  • Phone 9474 0777