South Perth Station Precinct works update: week commencing 3 April 2018
Approved works within the South Perth Station Precinct for the week commencing 3 April 2018:
LOCATION | DETAILS OF WORKS | WHO | DATE | TIME |
Construction site - abnormal works | ||||
Scott Street | Closure of Scott Street and traffic control on Melville Parade to facilitate crane lift. |
Danmar Developments | 3 April | 7am-1pm |
Construction site - general approvals | ||||
39 Mends Street (Echelon) |
Dewatering, Shotcreting piled walls, excavation, formwork and concrete pours. Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours. | Giorgi |
3-7 April | 7am-5pm |
21 Mends Street (Harper Terrace) | Reinforcement Steel deliveries & steel fixing, including delivery truck entering / exiting the site Concrete pouring to slabs/columns/walls, including concrete trucks entering / exiting the site Mobilisation of minor materials and equipment to site for Plumbing, Electrical & Mechanical Works Delivery and Installation of Formwork and Scaffold to Site, including delivery trucks entering / exiting the site. Delivery and installation of precast panels and AFS. |
Quest Apartments/Pindan | 3-7 April | 7am-5pm |
1 Stone Street | Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street. |
Danmar Developments |
3-7 April |
7am-5pm |
5 Harper Terrace (Reva) | General truck movements on Harper Terrace for dirt removal and minor concrete pours | Hanssen | 3-7 April | 7am-5pm |
96 Mill Point Road (Aurelia) | Footpath works on Harper Terrace. Harper Terrace closed to general traffic at northern site boundary. |
Hanssen | 3-7 April |
7am-5pm |
26 Charles Street | Bulk earthworks and reduced levels. Some head works for contiguous piles. Preparation for some concrete formwork and reinforcement. |
Pindan | 3-7 April | 7am-5pm |
Other works | ||||
South Perth Esplanade | Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road. | RAC | 3-7 April | 9am-5pm |
Mends Street (Mill Point Rd to South Perth Esplanade) | Closure of Mends Street for the Mends Street Community Market. | Mend Street Traders/CoSP | 8 April | 5am-2pm |
Upcoming works | ||||
21-23 Mends Street (Harper Terrace) | Early morning start concrete pour with truck access from Mill Point Road and South Perth Esplanade. | Quest Apartments/Pindan | 9 April | 4.30am-6pm |
Mends Street (Mill Point Rd to South Perth Esplanade) | Closure of Mends Street for the Mends Street Community Market. | Mend Street Traders/CoSP | 15 April | 5am-2pm |
Harper Terrace | Kerbing and pedestrian ramp | LGC Traffic | TBC | TBC |
21 Mends Street | Gas connections works | ATCO Gas | TBC | TBC |
To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.
Details of other road works in the City can be found on the construction and maintenance work page of the website.
Contact us
- Phone 9474 0777