South Perth Station Precinct works update: week commencing 3 April 2018

News Update 3 April 2018
Road Works SPSP Traffic

Approved works within the South Perth Station Precinct for the week commencing 3 April 2018:

LOCATION DETAILS OF WORKS WHO DATE TIME
Construction site - abnormal works
Scott Street Closure of Scott Street and traffic control on Melville Parade to facilitate crane lift.
Danmar Developments 3 April 7am-1pm
Construction site - general approvals
39 Mends Street (Echelon)
Dewatering, Shotcreting piled walls, excavation, formwork and concrete pours. Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours. Giorgi
3-7 April 7am-5pm
21 Mends Street (Harper Terrace) Reinforcement Steel deliveries & steel fixing, including delivery truck entering / exiting the site Concrete pouring to slabs/columns/walls, including concrete trucks entering / exiting the site Mobilisation of minor materials and equipment to site for Plumbing, Electrical & Mechanical Works Delivery and Installation of Formwork and Scaffold to Site, including delivery trucks entering / exiting the site. Delivery and installation of precast panels and AFS.
Quest Apartments/Pindan 3-7 April 7am-5pm
1 Stone Street Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street.
Danmar Developments
3-7 April
7am-5pm
5 Harper Terrace (Reva) General truck movements on Harper Terrace for dirt removal and minor concrete pours Hanssen 3-7 April 7am-5pm
96 Mill Point Road (Aurelia) Footpath works on Harper Terrace. Harper Terrace closed to general traffic at northern site boundary.
Hanssen 3-7 April
7am-5pm
26 Charles Street Bulk earthworks and reduced levels. Some head works for contiguous piles. Preparation for some concrete formwork and reinforcement.
Pindan 3-7 April 7am-5pm
Other works
South Perth Esplanade Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road. RAC 3-7 April 9am-5pm
Mends Street (Mill Point Rd to South Perth Esplanade)  Closure of Mends Street for the Mends Street Community Market.  Mend Street Traders/CoSP  8 April  5am-2pm 
Upcoming works
21-23 Mends Street (Harper Terrace)  Early morning start concrete pour with truck access from Mill Point Road and South Perth Esplanade. Quest Apartments/Pindan 9 April 4.30am-6pm 
Mends Street (Mill Point Rd to South Perth Esplanade)  Closure of Mends Street for the Mends Street Community Market.   Mend Street Traders/CoSP   15 April  5am-2pm  
Harper Terrace  Kerbing and pedestrian ramp   LGC Traffic TBC  TBC
21 Mends Street Gas connections works  ATCO Gas  TBC TBC

To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.

Details of other road works in the City can be found on the construction and maintenance work page of the website.

 



Contact us

For more information, please contact the City or Make a Request online.
  • Phone 9474 0777