South Perth Station Precinct works update: week commencing 12 February 2018
Approved works within the South Perth Station Precinct for the week commencing 12 February 2018:
LOCATION | DETAILS OF WORKS | WHO | DATE | TIME |
Construction site - general works | ||||
21-23 Mends Street (Harper Tce) | Early morning start concrete pour with truck access from Mill Point Road and South Perth Esplanade. | Quest Apartments/ Pindan | 14 and16 February | 4.30-5am |
39 Mends Street (Echelon) | Dewatering, Shotcreting piled walls, excavation, formwork and concrete pours. Truck movements on South Perth Esplanade. Full time traffic management in place on South Perth Esplanade during work hours | Giorgi | 12-17 February | 7am-5pm |
96 Mill Point Road (Aurelia) | General truck movements on Harper Terrace. Harper Terrace closed to general traffic at Mill Point Road end. Kerb works on Harper Terrace. Footpath reopened on Mill Point Road. | Hanssen | 12-17 February | 7am-5pm |
21-23 Mends Street (Harper Terrace) | Implementation of on street loading area on Harper Terrace contained within the work site boundary. Excavation and pouring of footings, steel deliveries, bubbledeck delivery and removal of excavated material off site resulting in truck movements impacting on Harper Terrace. Delivery and installation of precast panels and AFS. |
Quest Apartments/Pindan | 12-17 February | 7am-5pm |
1 Stone Street | Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street. |
Danmar Developments |
12-17 February |
7am-5pm |
5 Harper Terrace (Reva) | General truck movements on Harper Terrace. | Hanssen | 12-17 February | 7am-5pm |
Other works | ||||
8 Bowman Street | Verge works for communication installations. | C & M Communications | 14-16 February | 7am-4pm |
Richardson Street | Verge works for communication installations. | TPG/Trenchless | 12 February | 7am-5pm |
South Perth Explanade | Operation of Autonomous bus trials on South Perth Esplanade, Mill Point Close and Mill Point Road. |
RAC | 13-18 February | 9am-5pm |
Mends Street (Mill Point Rd to South Perth Esplanade) |
Closure of Mends Street for the Mends Street Farmers Market. |
Mend Street Traders/CoSP | 18 February | 5am-2pm |
Upcoming works | ||||
39 Mends Street (Echelon) | South Perth Esplanade road closure for concrete pour. Temporary road closure of South Perth Esplanade (Mends Street to west of Harper Terrace) for major concrete pour | Giorgi | TBC | 7pm-7am |
Mends Street (Mill Point Rd to South Perth Esplanade) | Closure of Mends Street for the Mends Street Farmers Market | Mend Street Traders/CoSP | 25 February | 5am-2pm |
South Perth Esplanade | Intellibus route and pace testing | RAC | 23 February | 12am-6am |
South Perth Esplanade | Gold Coast 2018 Commonwealth Games Queen's Baton Relay | Various | 24 February | TBC |
Labouchere Road | Lane closure on Labouchere Road (Richardson - Charles) northbound. Verge works for communication installations | TPG/Trenchless | TBC | 9am-3pm |
To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.
Details of other road works in the City can be found on the construction and maintenance work page of the website.
Contact us
- Phone 9474 0777