Road rehabilitation works on South Terrace

News Update 11 January 2022
Road Works
As part of the 2021/22 Capital Works Program, the City will be undertaking road rehabilitation works along South Terrace and Labouchere Road. Construction works are scheduled to commence on 17 January 2022 and will take approximately five weeks to complete. 

Night works

To avoid major disruptions, some elements of the works will be completed at night. These works are scheduled for 2 February, 3 February, 14 February and 15 February 2022. However, this could be subject to change. Working hours at night will be between 7pm to 5am.

Activities taking place at night include

  • Milling of the existing road surface
  • Road resurfacing with new asphalt
  • Traffic management.
Construction equipment and vehicle movements may create noise for adjacent residents. To ensure effective noise control, an out-of-hours Noise Management Plan has been prepared by the head contractor, West Coast Profilers Civil, and approved by the City of South Perth. 

Day time works

Day works are scheduled between 17 January to 25 February 2022 from 7am to 5pm.

Traffic management 

Temporary lane closures and detours will be implemented to facilitate the works. For the safety of road users and personnel, please follow signage and take care when driving in the area. Should you need to enter or exit your property while the works are in progress, we ask that you speak to the traffic controllers who will direct you through the work site. 

Elements of the works may unavoidably be disruptive. The City appreciates your support and cooperation during these works, our staff and contractors will make every effort to reduce any inconvenience.