Footpath construction - Greenock Ave, Como
In accordance with the 2019/20 Capital Works Program, the City will construct a new 1.8m wide concrete footpath at:
- Greenock Avenue between Coode Street and Robert Street, Como – commencing 14 April 2020.
The works will take approximately 3 weeks to complete, weather permitting.
Works will be confined to the hours of 7am to 5pm, Monday to Friday, although in order to complete the works it may be necessary to carry out some activities outside of these hours, including Saturdays.
Due to the impact Covid-19 on the City’s operations, these works have been scheduled earlier than originally planned.
The roads will be closed at certain times to through-traffic. Local residents will be permitted to access their properties, although some delays may occur. On-street parking will also be restricted to facilitate the works.
The front section of some resident’s crossovers may require modifications to allow for the installation of the new path. The head contractor Axiis Contracting will notify affected residents before the crossover reconstruction commences.
The works may also involve the removal and replacement of kerbing. If residents have reticulation on the kerb line it will be temporarily cut, capped and relocated away from the kerb. A notice will be placed in letterboxes upon reinstatement of reticulation. The City requests that residents test their systems within a two week period of receipt of the notice and if issues present please notify the City as soon as possible.