Approved works within the Canning Bridge Precinct for 4-10 March 2019:
LOCATION | DETAILS OF WORKS | WHO | DATE | TIME |
Construction site - abnormal works* | ||||
73 Park Street | Concrete pour utilising half road closure of Park Street at Henley Street. | Pyramid Constructions | 5 March | 7am-4.30pm |
Construction site - general approvals** | ||||
73 Park Street |
General construction operations contained on site. |
Pyramid Constructions |
4-9 March |
7am-5pm |
87 Robert Road |
General construction operations contained on site. |
PACT Construction |
4-9 March |
7am-7pm |
7 Mary Street | General construction operations, excavation and soil removal. | M Construction |
4-9 March | 7am-5pm |
Upcoming works | ||||
73 Park Street |
Concrete pour utilising road closure of Park Street at Henley Street. | Pyramid Constructions | 12 March | 7am-4.30pm |
Henley Street | Lateral shift with 3.0 metre eastbound lane on Henley Street for concrete pouring operations. | Pyramid Constructions | 20 March | 8am-2pm |
73 Park Street |
Concrete pour utilising road closure of Park Street at Henley Street. |
Pyramid Constructions |
27 March | 7am-4.30pm |
Lockhart Street | Water Corporation service upgrade works | Water Corporation | TBA | TBA |
To report a safety or accident hazard please contact the City or report the incident online via the City's Report It page.
Details of other road works in the City can be found on the construction and maintenance work page of the website.
*Abnormal works
Abnormal works are one off activities that require significant truck movements, obstructions to movement such as road closures and detours or works outside of the normal working hours. These works are subject to a separate approval process and are considered on an individual basis. Approvals may include the need to notify residents of the temporary change and in the case of works outside of normal working hours require subsequent approvals from the City’s Environmental Health Team and CEO.
**General Approvals
General approvals are granted to construction sites and long-term activities in the Station Precinct for daily activities such as general truck movements for deliveries and minor concrete pours. These works are only to be undertaken during normal working hours (7am – 7pm Monday -Saturday) and do not include works that will have a significant impact on access through/past the site area. General works are subject to a monthly approval process.