South Perth Station Precinct works update: week commencing 2 October 2017

News Update 29 September 2017
Road Works SPSP Traffic

Approved works within the South Perth Station Precinct for the week commencing 2 October 2017:

Location Details of works Who Date Time

Construction site - general works      
Scott Street  Closure of Scott Street to facilitate major crane lift.  Danmar Developments
 
 
4 October  7am-2pm 
39 Mends Street (Echelon) Dewatering and construction operations on site with truck access from South Perth Esplanade under traffic control. Verge and footpath closed on South Perth Esplanade with detours in place. Echelon/Giorgi 2-7 October
7am-5pm
96 Mill Point Rd (Aurelia) General truck movements for delivery of materials. Footpath closed on Mill Point Road from Labouchere to Harper for 2-3 weeks (subject to completion of reinstatement works on Mill Point Road). Aurelia/Hanssen  2-7 October 7am-5pm 
21-23 Mends Street (Harper Terrace)  Excavation and pouring of footings, steel deliveries and removal of excavated material off site resulting in truck movements impacting on Harper Terrace.  Quest Apartments/Pindan  2-7 October 7am-5pm 
1 Stone Street

Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street.

Danmar Developments 2-7 October
7am-5pm
  Short term traffic mangement      
Mends St (Mill Point Rd to South Perth Esplanade) 

Closure of Mends Street for the Mends Street Markets (Sunday Weekly) and temporary ‘No Parking’ and ‘No Entry’ signs in place (Harper Terrace).

 

Mends Street Traders / City of South Perth 

 
1 October  5am-2pm 
   Upcoming works      
South Perth Esplanade and Mends St Verge electrical service works and reinstatement with traffic management in place, pedestrian access unaffected.
 
Western Power contractors TBC  7am-5pm 





Contact us