New footpath construction McNabb Loop

News Update 11 August 2017
Maintenance Works

In accordance with the City’s 2017/18 Capital Works Program, a new 2 metre wide concrete footpath will be constructed in McNabb Loop from Murray Street, to join the existing footpath at Collier Retirement Village, Como.

The works will start the week commencing 14 August 2017, weather permitting.  

Once construction commences, the works are anticipated to be completed within six working days.

The works will take place between 7am and 4pm, Monday to Friday.

When completed this path will give safe pedestrian access for residents of Collier Retirement Village, Como Secondary College and other local residents.