Approved works within the South Perth Station Precinct for the week commencing 7 August 2017:
Location | Details of works | Who | Date | Time |
Construction site - general works | ||||
96 Mill Point Road | General truck movements for delivery of materials. Footpath closed on Mill Point Road from Labouchere to Harper for 2-3 weeks (subject to completion of reinstatement works on Mill Point Road). | Aurelia/Hanssen | 7-13 August | 7am-5pm |
77-79 South Perth Esplanade | Piling and construction operations on site with truck access from South Perth Esplanade under traffic control. Verge and footpath closed on South Perth Esplanade with detours in place. | Echelon/Giorgi | 7-13 August | 7am-5pm |
21-23 Mends Street (Harper Terrace) |
Piling works, steel deliveries and removal of excavated material off site impacting on Harper Terrace. Internal footing concrete pours. |
Millstream Arcade/Pindan | 7-13 August | 7am-5pm |
1 Stone Street | Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street. | Danmar Developments | 7-13 August | 7am-5pm |
77-79 South Perth Esplanade | Temporary road closure of South Perth Esplanade (Mends Street to west of Harper Terrace) for movement of construction equipment. | Echelon/Giorgi | 7 August | 9am-1pm |
Scott Street | Closure of Scott Street and traffic control on Melville Parade to facilitate major concrete pour. | Danmar Developments | 8-9 August | 7am-4pm |
96 Mill Point Road | Storage of sea containers for unloading on Harper Terrace adjacent to site boundary. | Aurelia/Hanssen | 8-10 August | 7am-5pm |
77-79 South Perth Esplanade | Temporary road closure of South Perth Esplanade (Mends Street to west of Harper Terrace) for movement of construction equipment. | Echelon/Giorgi | 11 August | 1-4pm |
|
Service works | |||
Mill Point Road (Onslow Street to Darley Street) |
Water main upgrade works |
Water Corporation contractors | 7-19 August | 9am-8pm |
Harper Terrace | Water main upgrade works. Partial road closures and exclusion zones. |
Water Corporation contractors | 7-19 August | 7am-7pm |
Labouchere Road (River View to Lyall Street) | Water main upgrade works. Lane closure northbound from Angelo Street to Lyall Street in place 24 hours a day until completion of works. Pedestrian management and detours in place. | Water Corporation contractors | 7-12 August | 7am-5pm |
152 Mill Point Road | Stop/slow management to allow for crane lift operations. | Wanneroo Crane Hire/Contraflow | 13 August | 7am-5pm |
Upcoming works (details to be confirmed)
Location | Details of works | Who | Date | Time |
Mill Point Road (Onslow - Darley) | Road closure. Mends Street to Onslow Road both directions to allow installation of workzone barrier. Road to be reopened as soon as installation works are completed. |
Water Corporation contractors | Barrier installation date to be confirmed. | 9pm-6am |
Mill Point Road (Onslow - Darley) | Water main upgrade works. Lane closure westbound (24/7 with workzone barrier in place to provide protect to excavation) with footpath closure and detour for connection works. Work hours will be 7am-7pm Monday to Friday and 7am-5pm Saturday. | Water Corporation contractors | Barrier installation date to be confirmed. | 24/7 |
Mill Point Road (Labouchere Road - Harper Terrace) | Resurfacing and kerbing works. Lane closure, eastbound road closure on Mill Point Road. Detours will be provided for all traffic. | Water Corporation contractors | TBC | TBC |
20 Harper Terrace | Power connection works undertaken in verge. | Western Power contractor/ Taborda | 15 August | 7am-5pm |
96 Mill Point Road | Storm water drainage connection works in Harper Terrace (adjacent to 20 Harper Terrace), access permitted from Mill Point Road, no through access available on Harper Terrace. | 12-13 August | 7am-5pm | |
96 Mill Point Road | Western Power connection works in Harper Terrace (adjacent to Southshore development), access permitted from Mill Point Road, no through access available on Harper Terrace. | Aurelia/ Hanssen | 14-19 August | 7am-5pm |
152 Mill Point Road | Contraflow of traffic (one lane each direction) to allow for crane lift operations. | Wanneroo Crane Hire /Contraflow | 2 and 23 September | 7am-5pm |
Contact us