South Perth Station Precinct works update: week commencing 10 July 2017
Approved works within the South Perth Station Precinct for the week commencing 10 July 2017:
Location | Details of works | Who | Date | Time |
Scott Street |
Closure of Scott Street and traffic control on Melville Parade to facilitate major deliveries. |
Danmar Developments |
10 July | 7am-2pm |
77-79 South Perth Esplanade | Piling and construction operations on site with truck access from South Perth Esplanade under traffic control. Verge and footpath closed on South Perth Esplanade with detours in place. | Echelon/Giorgiou | 10-16 July | 7am-5pm |
96 Mill Point Road | General truck movements for delivery of materials. Footpath closed on Mill Point Road from Labouchere Road to Harper Terrace for 5-7 weeks. |
Aurelia / Hanssen | 10-16 July | 7am-5pm |
21-23 Mends Street (Harper Terrace) |
Piling works, steel deliveries and removal of excavated material off site impacting Harper Terrace. |
Millstream Arcade/Pindan | 10-16 July | 7am-5pm |
1 Stone Street | Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street. | Danmar Developments | 10-16 July | 7am-5pm |
Mill Point Road (Onslow Street to Darley Street) |
Water main upgrade works. One traffic lane each direction (10am-8pm) for drilling works. Lane closure westbound (9am-3pm) with footpath closure and detour for connection works. |
Water Corporation Contractors | 10-25 July | 10am-8pm |
Mill Point Road (Darley Street to Harper Terrace) and Mends Street |
Water main upgrade works. Night works with road closures and detours in place at Mill Point Road/Mends Street intersection (two nights only). |
Water Corporation Contractors |
10-25 July | 9pm-5am |
Harper Terrace |
Water main upgrade works. Partial road closures and exclusion zones. |
Water Corporation Contractors | 10-27 July | 7am-7pm |
Upcoming works (details to be confirmed)
Location | Details of works | Who | Date | Time |
Labouchere Road (River View Street to Lyall Street) |
Water main upgrade works. Lane closure northbound from Angelo St to Lyall Street. Pedestrian management and detours in place. |
Water Corporation Contractors | 17 July - 21 August | 7am-5pm |
Scott Street | Closure of Scott Street and traffic control on Melville Parade to facilitate concrete pour. |
Danmar Developments |
27 July | 7am-2pm |
Contact us