South Perth Station Precinct works update: week commencing 29 May 2017
Approved works within the South Perth Station Precinct for the week commencing 29 May 2017:
Location | Details of works | Who | Date | Time |
77-79 South Perth Esplanade | Footpath closure and pedestrian detours on Mends Street and South Perth Esplanade. | Echelon/Giorgi | 29 May-3 Jun | 7am-5pm |
77-79 South Perth Esplanade | Temporary road closure of South Perth Esplanade (Mends Street to Harper Terrace) for movement of construction equipment. |
Echelon/Giorgi | 30 May | 10am-2pm |
21-23 Mends Street (Harper Terrace) | Piling works and removal of excavated material off site impacting on Harper Terrace. | Millstream Arcade/Pindan | 29 May-3 Jun | 7am-5pm |
96 Mill Point Road | General truck movements for delivery of materials. Footpath closed on Mill Point Road from Labouchere Road to Harper Terrace for 5-7 weeks. | Aurelia/Hanssen |
29 May-3 Jun |
7am-5pm |
6 Mill Point Road | Concrete pour with increased truck movements and restrictions to access on Harper Terrace. |
Aurelia/Hanssen |
29 May | 7am - 12pm |
20 Harper Terrace | Internal works on site. | Cooktown Constructions | 29 May-3 Jun | 7am-5pm |
1 Stone Street | Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street. | Danmar Developments | 29 May-3 Jun | 7am-5pm |
Mill Point Road (north) | Installation of upgrade to existing gas main. | ATCO Gas | 29 May-3 Jun | 9am-3pm |
Onslow Street & Angelo Street | Water main upgrade works. | Densford Civil/ Water Corp | 29 May-3 Jun | 8am-5pm |
Bowman Street | Installation of upgrade to existing gas main. | ATCO Gas | 29 May-3 Jun | 8am-4pm |
Mill Point Road (Onslow Street – Darley Street) | Water main upgrade works - lane closure westbound (9am-3pm) with footpath closure and detour. | Water Corporation Contractors | 29 May-3 Jun | 7am- 5pm |
Scott Street (Stone St - Melville Pde) | Road closure to facilitate concrete pour. | Danmar Developments |
29 May | 7am-5pm |
Labouchere Road (southbound) | Lane and footpath closure to facilitate footpath repair works. Footpath closure to remain in place for 24 hours. |
City of South Perth | 29 May | 7am - 3pm |
Upcoming works (details to be confirmed)
Location | Details of works | Who | Date | Time |
Mill Point Road (Darley Street- Mends Street) and Mends Street | Water main upgrade works - partial road closure and detour, lane closures and pedestrian management. | Water Corporation Contractors | TBC | 9am-5pm |
Labouchere Road, Mill Point Road and Harper Terrace | Water main upgrade works. | Water Corporation Contractors | Commencing late May 2017 | TBC |
Harper Terrace and Mill Point Road | Lane and verge closures on Mill Point Road and Harper Terrace to facilitate sewer repair works. | Water Corporation Contractors | TBC (commencing May 2017) | 9am-3pm |
Millers Pool Car Park |
Parking closure and pedestrian management for additional bridge pier works. | Saunders |
TBC |
7am-5pm |
Scott Street and Stone Street | Drainage upgrade works, lane closures on Scott Street and Stone Street. | City of South Perth | TBC | 7am-5pm |
Contact us
For more information, please contact the City or Make a Request online.
- Phone 9474 0777