South Perth Station Precinct works update: week commencing 15 May 2017
Approved works within the South Perth Station Precinct for the week commencing 15 May 2017:
Installation of upgrade to existing gas mainLocation | Details of works | Who | Date | Time |
77-79 South Perth Esplanade | Footpath closure and pedestrian detours on Mends Street and South Perth Esplanade. | Echelon/Giorgi | 15-20 May | 7am-5pm |
21-23 Mends Street (Harper Terrace) | Demolition works with associated truck movements, closure of footpath on Harper Terrace and pedestrian management. | Millstream Arcade/Pindan | 15-20 May | 7am-5pm |
96 Mill Point Road | Temporary closure of Harper Terrace. General truck movements for delivery of materials. Footpath closed on Mill Point Road from Labouchere Road to Harper Terrace for 6-8 weeks. | Aurelia/Hanssen |
15-20 May |
7am-5pm |
96 Mill Point Road | Concrete pour with increased truck movements and restrictions to access on Harper Terrace. | Aurelia/Hanssen | 16 May | 7am-12pm |
Labouchere Road (Mill Point Road - Mends Street) | Southbound lane closure to support dewatering truck movements. | Civic Heart/Hanssen | 15-20 May | 24/7 |
20 Harper Terrace | Internal works on site. | Cooktown Constructions | 15-20 May | 7am-5pm |
1 Stone Street | Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street. | Danmar Developments | 15-20 May | 7am-5pm |
Mill Point Road (north) and Labouchere Road | Installation of upgrade to existing gas main. | ATCO Gas | 15-20 May | 9am-3pm |
Onslow Road & Angelo Street | Water main upgrade works. | Densford Civil/ Water Corp | 15-20 May | 8am-5pm |
Bowman Street | Installation of upgrade to existing gas main. | ATCO Gas | 15-20 May | 8am-4pm |
100 Mill Point Road | Footpath and lane closure to facilitate reinstatement works. | Western Power/ Power on Cabling | 17-18 May | 9am-3pm |
Short term low impact works
Location | Details of works | Who | Date | Time |
Millers Pool car park | Parking closure and pedestrian management for bridge pier works. | Saunders | 15-21 May | 7am-5pm |
Upcoming works (details to be confirmed)
Location | Details of works | Who | Date | Time |
Mill Point Road, Labouchere Road | Installation of upgrade to existing gas main. Works on Mill Point Road and Labouchere Road will be undertaken from 9am-3pm. | ATCO Gas | 15 May-9June | 8am-4pm |
Mill Point Road (Onslow Street - Darley Street) | Water main upgrade works - Partial Road closure and detour, lane closures and pedestrian management. | Water Corporation Contractors |
22 May-2June | 7am-7pm |
21-23 Mends Street (Harper Terrace) | Piling works and removal of excavated material off site impacting on Harper Terrace. | Millstream Arcade/Pindan | 22 May-ongoing | 7am-5pm |
Mill Point Road (Darley Street- Mends Street) and Mends Street | Water main upgrade works - Partial Road closure and detour, lane closures and pedestrian management. | Water Corporation Contractors | TBC | 9am-5pm |
Labouchere Road, Mill Point Road and Harper Terrace | Water main upgrade works. | Water Corporation Contractors | Commencing late May 2017 | TBC |
Harper Terrace and Mill Point Road | Lane and verge closures on Mill Point Road and Harper Terrace to facilitate sewer repair works. | Water Corporation Contractors | TBC (commencing May 2017) | 9am-3pm |
77-79 South Perth Esplanade |
Temporary road closure for movement of construction equipment. | Echelon/Giorgi |
30 May |
TBC |
Scott Street and Stone Street | Drainage upgrade works, lane closures on Scott Street and Stone Street. | City of South Perth | TBC | 7am-5pm |
Contact us
For more information, please contact the City or Make a Request online.
- Phone 9474 0777