South Perth Station Precinct works update: week commencing 15 May 2017

News Update 12 May 2017
Road Works SPSP Traffic

Approved works within the South Perth Station Precinct for the week commencing 15 May 2017:

Installation of upgrade to existing gas main
Location Details of works  Who  Date  Time 
77-79 South Perth Esplanade Footpath closure and pedestrian detours on Mends Street and South Perth Esplanade.  Echelon/Giorgi 15-20 May 7am-5pm
21-23 Mends Street (Harper Terrace)  Demolition works with associated truck movements, closure of footpath on Harper Terrace and pedestrian management. Millstream Arcade/Pindan  15-20 May 7am-5pm 
96 Mill Point Road Temporary closure of Harper Terrace. General truck movements for delivery of materials. Footpath closed on Mill Point Road from Labouchere Road to Harper Terrace for 6-8 weeks. Aurelia/Hanssen

15-20 May

7am-5pm
96 Mill Point Road  Concrete pour with increased truck movements and restrictions to access on Harper Terrace. Aurelia/Hanssen  16 May 7am-12pm 
Labouchere Road (Mill Point Road - Mends Street) Southbound lane closure to support dewatering truck movements. Civic Heart/Hanssen 15-20 May 24/7
20 Harper Terrace Internal works on site. Cooktown Constructions 15-20 May 7am-5pm
1 Stone Street  Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street. Danmar Developments 15-20 May 7am-5pm 
Mill Point Road (north) and Labouchere Road Installation of upgrade to existing gas main. ATCO Gas 15-20 May  9am-3pm 
Onslow Road & Angelo Street Water main upgrade works. Densford Civil/ Water Corp 15-20 May 8am-5pm
Bowman Street Installation of upgrade to existing gas main. ATCO Gas 15-20 May 8am-4pm
100 Mill Point Road  Footpath and lane closure to facilitate reinstatement works.  Western Power/ Power on Cabling  17-18 May  9am-3pm 

 

Short term low impact works

Location Details of works Who Date Time
Millers Pool car park Parking closure and pedestrian management for bridge pier works. Saunders 15-21 May 7am-5pm

Upcoming works (details to be confirmed)

Location  Details of works    Who Date  Time 
Mill Point Road, Labouchere Road Installation of upgrade to existing gas main. Works on Mill Point Road and Labouchere Road will be undertaken from 9am-3pm. ATCO Gas  15 May-9June 8am-4pm
Mill Point Road (Onslow Street - Darley Street) Water main upgrade works - Partial Road closure and detour, lane closures and pedestrian management. Water Corporation Contractors
22 May-2June 7am-7pm
21-23 Mends Street (Harper Terrace)   Piling works and removal of excavated material off site impacting on Harper Terrace. Millstream Arcade/Pindan  22 May-ongoing  7am-5pm 
Mill Point Road (Darley Street- Mends Street) and Mends Street  Water main upgrade works - Partial Road closure and detour, lane closures and pedestrian management.  Water Corporation Contractors  TBC  9am-5pm
Labouchere Road, Mill Point Road and Harper Terrace  Water main upgrade works.  Water Corporation Contractors   Commencing late May 2017  TBC 
Harper Terrace and Mill Point Road Lane and verge closures on Mill Point Road and Harper Terrace to facilitate sewer repair works. Water Corporation Contractors TBC (commencing May 2017) 9am-3pm
77-79 South Perth Esplanade
Temporary road closure for movement of construction equipment. Echelon/Giorgi
30 May
TBC
Scott Street and Stone Street   Drainage upgrade works, lane closures on Scott Street and Stone Street.  City of South Perth  TBC  7am-5pm 


Contact us

For more information, please contact the City.