South Perth Station Precinct works update: week commencing 8 May 2017

News Update 8 May 2017
Road Works SPSP Traffic

Approved works within the South Perth Station Precinct for the week commencing 8 May 2017:

Installation of upgrade to existing gas main
Location Details of works  Who  Date  Time 
77-79 South Perth Esplanade Foot path closure and pedestrian detours on Mends Street and South Perth Esplanade.  Echelon/Giorgi 8-13 May 7am-5pm
21-23 Mends Street (Harper Terrace)  Demolition works with associated truck movements, closure of footpath on Harper Terrace and pedestrian management. Millstream Arcade/Pindan  8-13 May 7am-5pm 
96 Mill Point Road Temporary closure of Harper Terrace. Large truck deliveries entering off Mill Point Road. Aurelia/Hanssen

8-13 May

7am-5pm
Labouchere Road (Mill Point Road - Mends Street) Southbound lane closure to support dewatering truck movements. Civic Heart/Hanssen 8-13 May 24/7
20 Harper Terrace Internal works on site. Cooktown Constructions 8-13 May 7am-5pm
1 Stone Street  Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street. Danmar Developments 8-13 May 7am-5pm 
Mends Street Installation of upgrade to existing gas main ATCO Gas 8-13 May 8am-4pm
Onslow Road & Angelo Street Water main upgrade works. Densford Civil / Water Corp 8-13 May 7am-5pm
 Bowman Street Installation of upgrade to existing gas main   ATCO Gas 8-13 May 8am-4pm

 

Short term low impact works

Location Details of works Who Date Time
Millers Pool car park Parking closure and pedestrian management for bridge pier works. Saunders 8-13 May 7am-5pm

Upcoming works (details to be confirmed)

Location  Details of works    Who Date  Time 
Mill Point Road, Labouchere Road and Bowman Street Installation of upgrade to existing gas main. Works on Mill Point Road and Labouchere Road will be undertaken from 9am-3pm. ATCO Gas  15-31 May 8am-4pm
Mill Point Road (Onslow - Darley) Water main upgrade works - Lane closure and aftercare Water Corporation Contractors
Commencing 22 May 2017 TBC
Labouchere Road; Mill Point Road and Harper Terrace  Water main upgrade works Water Corporation Contractors Commencing late May 2017 7am-5pm
100 Mill Point Road Footpath and lane closure to facilitate reinstatement works. Western Power / Power on Cabling 17-18 May 2017 9am-3pm
Harper Terrace and Mill Point Road Lane and verge closures on Mill Point Road and Harper Terrace to facilitate sewer repair works. Water Corporation Contractors TBC
(commencing May 2017) 
 TBC
134 Mill Point Road Lane closures (both directions) for street light replacement.  Western Power / UASG 15-19 May 2017 8pm-5am
77-79 South Perth Esplanade
Temporary road closure for movement of construction equipment. Echelon / Giorgi
TBC (late May 2017)
TBC