South Perth Station Precinct works update: week commencing 24 April 2017

News Update 24 April 2017
Road Works SPSP Traffic

Approved works within the South Perth Station Precinct for the week commencing 24 April 2017:

Location Details of works  Who  Date  Time 
77-79 South Perth Esplanade Foot path closure and pedestrian detours on Mends Street and South Perth Esplanade.  Echelon/Giorgi 24-29 April 7am-5pm
21-23 Mends Street (Harper Terrace)  Demolition works with associated truck movements, closure of footpath on Harper Terrace and pedestrian management. Millstream Arcade/Pindan  24-29 April 7am-5pm 
96 Mill Point Road Temporary closure of Harper Terrace. Large truck deliveries entering off Mill Point Road. Aurelia/Hanssen

24-29 April

7am-5pm
Labouchere Road (Mill Point Road - Mends Street) Southbound lane closure to support dewatering truck movements. Civic Heart/Hanssen 24-29 April 24/7
20 Harper Terrace Internal works on site. Cooktown Constructions 24-29 April 7am-5pm
1 Stone Street  Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street. Danmar Developments 24-29 April 7am-5pm 
 Mill Point Road (Mends - Labouchere)  Parking closure and pedestrian management for bridge pier works. Civic Heart/Hanssen 26-28 April 9am-
3pm

 

Short term low impact works

Location Details of works Who Date Time
Millers Pool car park Westbound kerb side lane closure to facilitate removal/relocation of fencing. Saunders 18-22 April 7am-5pm

 

Upcoming works (details to be confirmed)

Location  Details of works    Who Date  Time 
Mends Street, Labouchere Road and Bowman Street Installation of upgrade to existing gas main. ATCO Gas  1 May 2017 7am-5pm
Labouchere Road; Mill Point Road and Harper Terrace  Water main upgrade works Water Corporation Contractors TBC
(commencing April 2017)
7am-5pm
96 Mill Point Road Lane closures on Mill Point Road to facilitate gantry remova. Hanssen  3-10 May TBC
 Harper Terrace and Mill Point Road  Lane and verge closures on Mill Point Road and Harper Terrace to facilitate sewer repair works.  Water Corporation Contractors TBC
(commencing May 2017) 
 TBC