South Perth Station Precinct works update: week commencing 20 March 2017
Approved works within the South Perth Station Precinct for the week commencing 20 March 2017:
Location | Details of works | Who | Date | Time |
77-79 South Perth Esplanade | Demolition works, minor truck movements. | Echelon/Giorgi | 20 March - 25 March | 7am to 5pm |
21-23 Mends Street (Harper Terrace) | Demolition works with associated truck movements, closure of footpath on Harper Terrace and pedestrian management. | Millstream Arcade/Pindan | 20 March - 25 March | 7am to 5pm |
96 Mill Point Road | Temporary closure of Harper Terrace. Excavation works resulting in truck movements on Harper Terrace and South Perth Esplanade. Large truck deliveries entering off Mill Point Road. | Aurelia / Hanssen |
20 March - 25 March |
7am to 5pm |
Labouchere Road (Mill Point Road - Mends Street) | Southbound lane closure to support dewatering truck movements. | Civic Heart / Hanssen | 20 March - 25 March | 6am to 6pm |
Labouchere Road (Mill Point Road - Mends Street) | Traffic control on Labouchere Road and Bowman Street to facilitate trucks reversing in to site for equipment removal. | Civic Heart / Hanssen | 23 March - 25 March | 9am to 3pm |
20 Harper Terrace | Internal works. | Cooktown Constructions | 20 March - 25 March | 7am to 5pm |
Labouchere Road (Hardy Street - Richardson Street) and Charles Street | Lane closures and pedestrian management. | City of South Perth | 20 March | 9am to 4pm |
Short term low impact works
Location | Details of works | Who | Date | Time |
Millers Pool car park | Parking closure and pedestrian management for bridge pier works. | Saunders | 20 March - 24 March | 7am to 5pm |
73 Stone Street | Verge closure, pedestrian management and speed restrictions. | SPEC Construction | 20 March - 22 March | 7am to 5pm |
Upcoming works (details to be confirmed)
Location | Details of works | Who | Date | Time |
96 Mill Point Road | Closure of Harper Terrace to facilitate concrete pours on Aurelia Site. | Aurelia / Hanssen | 20 March onwards | 7am to 5pm |
1 Stone Street | Internal works on site | 27 March onwards | ||
Mends Street, Labouchere Road & Bowman Street | Installation of upgrade to existing gas main. | ATCO Gas | TBC (commencing March 2017) | 7am to 5pm |
Labouchere Road; Mill Point Road and Harper Terrace | Water main upgrade works | Water Corporation Contractors | TBC (commencing March 2017) | 7am to 5pm |
Contact us
- Phone 9474 0777
- Email enquiries@southperth.wa.gov.au