South Perth Station Precinct works update: week commencing 20 March 2017

News Update 17 March 2017
Road Works SPSP Traffic

Approved works within the South Perth Station Precinct for the week commencing 20 March 2017:

Location Details of works  Who  Date  Time 
77-79 South Perth Esplanade Demolition works, minor truck movements.   Echelon/Giorgi 20 March - 25 March 7am to 5pm
21-23 Mends Street (Harper Terrace)  Demolition works with associated truck movements, closure of footpath on Harper Terrace and pedestrian management. Millstream Arcade/Pindan  20 March - 25 March 7am to 5pm 
96 Mill Point Road Temporary closure of Harper Terrace. Excavation works resulting in truck movements on Harper Terrace and South Perth Esplanade. Large truck deliveries entering off Mill Point Road. Aurelia / Hanssen

20 March - 25 March

7am to 5pm
Labouchere Road (Mill Point Road - Mends Street) Southbound lane closure to support dewatering truck movements. Civic Heart / Hanssen 20 March - 25 March  6am to 6pm
Labouchere Road (Mill Point Road - Mends Street)  Traffic control on Labouchere Road and Bowman Street to facilitate trucks reversing in to site for equipment removal. Civic Heart / Hanssen 23 March - 25 March 9am to 3pm 
20 Harper Terrace Internal works. Cooktown Constructions 20 March - 25 March 7am to 5pm
Labouchere Road (Hardy Street - Richardson Street) and Charles Street  Lane closures and pedestrian management. City of South Perth  20 March 9am to 4pm

Short term low impact works

Location Details of works Who Date Time
Millers Pool car park Parking closure and pedestrian management for bridge pier works. Saunders 20 March - 24 March 7am to 5pm
73 Stone Street Verge closure, pedestrian management and speed restrictions. SPEC Construction  20 March - 22 March  7am to 5pm 

Upcoming works (details to be confirmed)

Location  Details of works    Who Date  Time 
96 Mill Point Road Closure of Harper Terrace to facilitate concrete pours on Aurelia Site. Aurelia / Hanssen 20 March onwards 7am to 5pm
1 Stone Street  Internal works on site    27 March onwards   
Mends Street, Labouchere Road & Bowman Street Installation of upgrade to existing gas main. ATCO Gas  TBC (commencing March 2017) 7am to 5pm
Labouchere Road; Mill Point Road and Harper Terrace  Water main upgrade works Water Corporation Contractors TBC (commencing March 2017) 7am to 5pm

Contact us

For more information, please contact the City.