South Perth Station Precinct works update: week commencing 13 March 2017

News Update 13 March 2017
Road Works SPSP Traffic

Approved works within the South Perth Station Precinct for the week commencing 13 March 2017:

Location Details of works  Who  Date  Time 
77-79 South Perth Esplanade Demolition works, minor truck movements.   Echelon/Giorgi 13 March - 18 March 7am to 5pm
21-23 Mends Street (Harper Terrace)  Demolition works with associated truck movements, closure of footpath in Harper Terrace and pedestrian management. Millstream Arcade/Pindan  13 March - 18 March 7am to 5pm 
96 Mill Point Road Temporary closure of Harper Terrace. Excavation works resulting in truck movements on Harper Terrace and South Perth Esplanade. Aurelia / Hanssen

13 March - 18 March

7am to 5pm
Labouchere Road (Mill Point Road - Mends Street) Southbound lane closure to support dewatering truck movements. Civic Heart / Hanssen 13 March - 18 March  7am to 5pm
Labouchere Road (Mill Point Road - Mends Street)  Traffic control on Labouchere Road and Bowman Street to facilitate trucks reversing in to site for equipment removal. Civic Heart / Hanssen 17 March 9am to 3pm 
20 Harper Terrace Internal works. Cooktown Constructions 13 March - 18 March 7am to 5pm
Labouchere Road (Hardy Street - Richardson Street) and Charles Street  Lane closures and pedestrian management. City of South Perth  17 March 9am to 4pm
Labouchere Road (Lyall St - Bowman St)  Lane closures and pedestrian management for Western Power works. TX Civil Logistics / Taborda 14 March 9am to 3pm

Upcoming works (details to be confirmed)

Location  Details of works    Who Date  Time 
96 Mill Point Road Closure of Harper Terrace to facilitate concrete pours on Aurelia Site. Aurelia / Hanssen 20 March onwards 7am to 5pm
Mends Street & Labouchere Road Installation of upgrade to existing gas main. ATCO Gas  TBC (likely commencement March 2017) 7am to 5pm
Labouchere Road; Mill Point Road and Harper Terrace  Water main upgrade works Water Corporation Contractors TBC (likely commencement March 2017) 7am to 5pm
 20 Harper Terrace Half road closure on Harper Terrace to facilitate concrete panel lifts.  Cooktown Constructions  TBC 9am to 2pm

Contact us