Approved works within the South Perth Station Precinct for the week commencing 3 April 2017:
Location | Details of works | Who | Date | Time |
77-79 South Perth Esplanade | Lane closures and traffic control for sewer works. Foot path closure and pedestrian detours on Mends Street. | Echelon/Giorgi | 3-7 Aprill | 7am to 5pm |
21-23 Mends Street (Harper Terrace) | Demolition works with associated truck movements, closure of footpath on Harper Terrace and pedestrian management. | Millstream Arcade/Pindan | 3-8 April | 7am to 5pm |
96 Mill Point Road | Temporary closure of Harper Terrace. Excavation works resulting in truck movements on Harper Terrace and South Perth Esplanade. Large truck deliveries entering off Mill Point Road. | Aurelia / Hanssen |
3-8 April |
7am to 5pm |
96 Mill Point Road |
Significant concrete pour resulting in increased concrete truck movements. Traffic management of Harper Terrace for truck holding and pouring activities. | Aurelia / Hanssen | 4 April | 5am to 5pm |
Labouchere Road (Mill Point Road - Mends Street) | Southbound lane closure to support dewatering truck movements. | Civic Heart / Hanssen | 3-8 April | 6am to 6pm |
Labouchere Road (Mill Point Road - Mends Street) | Traffic control on Labouchere Road and Bowman Street to facilitate trucks reversing in to site for equipment removal. | Civic Heart / Hanssen | 3-4 April | 9am to 3pm |
20 Harper Terrace | Internal works on site. | Cooktown Constructions | 3-4 April | 7am to 5pm |
1 Stone Street | Internal works on site with pedestrian detours and parking area closures for deliveries on Scott Street and Stone Street. | Danmar Developments | 3-4 April | 7am to 5pm |
Short term low impact works
Location | Details of works | Who | Date | Time |
Millers Pool car park | Parking closure and pedestrian management for bridge pier works. | Saunders | 3-8 April | 7am to 5pm |
Upcoming works (details to be confirmed)
Location | Details of works | Who | Date | Time |
Mends Street, Labouchere Road & Bowman Street | Installation of upgrade to existing gas main. | ATCO Gas | TBC | 7am to 5pm |
Labouchere Road; Mill Point Road and Harper Terrace | Water main upgrade works | Water Corporation Contractors | TBC | 7am to 5pm |