EJ Reserve Redevelopment Update March 2017

News Update 28 March 2017
Ernest Johnson Reserve

Initial site works for the Ernest Johnson Reserve redevelopment commenced in February 2017. 

To date, works completed by PACT Construction Pty Ltd have included:

  • Ongoing earthworks
  • New sewer lines installed
  • Storm water pits installed
  • Retaining walls built
  • Detailed excavation and formwork
  • Pouring of concrete pad and footings.

Works will be completed in two stages with the first stage including construction of new clubrooms, parking facilities and associated infrastructure. The first stage of the project is progressing well and remains on schedule for completion at the end of 2017.

Contact us

For more information, please contact the City or Make a Request online.
  • Phone 9474 0777